• SES Exhibition Lounge Scenic Fabrication at RICEC, Riyadh

    Evolution Scenic temporary exhibition architecture installed at Riyadh International Convention and Exhibition Center.

    PROJECT OVERVIEW


    Evolution Scenic designed, fabricated, installed and dismantled the SES Exhibition Lounge for the Saudi Event Show 2023, delivered at the Riyadh International Convention & Exhibition Center (RICEC).


    The project was developed as a complete temporary exhibition environment rather than a series of individual branded elements. The scenic package combined architectural wall construction, custom joinery, furniture integration, technical displays, dimensional branding and an overhead suspended fabric treatment within one coordinated lounge.


    The physical environment needed to support several functions within the same footprint. Visitors required comfortable seating areas, standing networking positions, coffee-service facilities and access to digital exhibition information, while the overall space still needed to read as one visually connected installation.


    Evolution Scenic therefore approached the lounge as a piece of temporary exhibition architecture. White scenic walls established the main enclosure and visual framework. Contrasting dark joinery helped define functional areas, while the suspended blue fabric feature created a recognisable architectural layer above the lounge.


    The project also brought together several Evolution disciplines. Evolution Scenic delivered the primary scenic construction and custom-fabricated elements. Evolution Furniture supplied the chairs, sofas and coffee tables, while Evolution Technical supplied the integrated display screens.


    Evolution Scenic fabricated the dimensional logos used within the lounge. Wall graphics and printed fabric were produced by specialist outsourced suppliers and coordinated into the finished environment.


    The confirmed overall project programme was 15 days, including the scenic delivery process. Following the Saudi Event Show, Evolution Scenic was also responsible for dismantling the temporary installation.

    Evolution Scenic modular SES Exhibition Lounge with suspended blue fabric ceiling in Riyadh.

    MODULAR SCENIC CONSTRUCTION & FABRICATION


    The main SES Exhibition Lounge environment was manufactured as workshop-built modular scenic sections before being transported to RICEC for installation.


    The confirmed construction materials included MDF, plywood, timber framing, metal framing, acrylic and laminate.


    Using a combination of materials allowed different parts of the lounge to be fabricated according to their functional and visual requirements. MDF and plywood provided suitable substrates for scenic walls and custom joinery, while timber and metal framing supported the internal construction of the modular elements.


    The scenic structures were manufactured in sections rather than constructed entirely inside the exhibition hall. This meant much of the cutting, assembly, preparation and finishing could be completed under controlled workshop conditions before delivery.


    For temporary scenic construction, modular fabrication is particularly useful where site access and installation periods are restricted. The methodology allows substantial sections of an exhibition environment to arrive at the venue already manufactured and finished, reducing the amount of primary construction required on the exhibition floor.


    The modular sections also needed to connect accurately once positioned on site. Alignment between scenic walls, custom counters, technical openings and neighbouring structures was therefore important to achieving the finished appearance.


    The construction had to visually conceal the temporary nature of the build. Once assembled, the environment needed to appear as a continuous interior rather than a visible collection of transportable modules.


    Particular attention would normally be given to junctions, panel alignment, edge conditions and connection points when producing modular scenic environments. These are normal Evolution Scenic fabrication considerations rather than confirmed project-specific technical details.


    The modular methodology also supported the eventual dismantling of the lounge. Because the environment was temporary from the outset, the construction needed to be suitable for installation and subsequent removal after the exhibition.


    No confirmed information has been supplied regarding exact panel thicknesses, internal framing dimensions or mechanical fixing systems, so these details are not assumed.

    Modular white scenic wall construction surrounding fitted lounge seating and display screens.

    CUSTOM JOINERY, COFFEE BAR & FURNITURE


    Custom joinery played an important role in transforming the lounge from a basic exhibition enclosure into a functional hospitality and networking environment. One of the principal fabricated elements was the custom coffee bar. Rather than placing a standard catering counter inside the lounge, the bar was developed as part of the wider scenic architecture. Its darker finish created visual contrast against the predominantly white scenic walls and helped establish a defined hospitality zone within the environment.


    The coffee bar had to function operationally while maintaining the standard of finish expected from the surrounding scenic construction. This relationship between functionality and appearance is a key consideration in exhibition joinery, where counters and furniture are often highly visible components of the completed environment.


    Evolution Scenic also fabricated custom standing networking tables specifically for the project.

    Producing these tables as bespoke pieces allowed their appearance to remain consistent with the lounge rather than introducing unrelated off-the-shelf furniture into the scenic composition.

    Their integration contributed to the overall visual language of the space while providing practical standing positions for informal discussions and networking. The wider furniture package was supplied by Evolution Furniture.


    The supplied furniture was positioned within the zones created by the scenic construction, allowing the modular walls, furniture and circulation areas to function together.

    This coordination between fabricated joinery and loose furniture helped maintain consistency throughout the lounge. The custom elements established the architectural character, while the furniture completed the operational seating and hospitality requirements. The project therefore involved more than manufacturing wall structures. Scenic fabrication extended into the functional components visitors physically interacted with throughout the exhibition.

    Evolution Scenic fabricated coffee bar framed by white scenic walls and blue ceiling fabric.

    SCENIC FINISHES, GRAPHICS & BRAND INTEGRATION


    The fabricated scenic environment received PU-painted finishes. PU paint was used across the fabricated scenic surfaces to create the clean, controlled appearance required throughout the lounge. The predominantly white architectural treatment provided a neutral scenic background, while darker elements such as the coffee bar introduced stronger contrast between different functional areas.


    A high-quality scenic finish is particularly important on exhibition projects because walls, counters and branded elements are viewed at relatively close range. Surface preparation, edge quality and consistency across adjoining fabricated sections all contribute to the final presentation. 

    Evolution Scenic also fabricated the dimensional logos used within the SES Exhibition Lounge. Rather than relying entirely on printed branding, the dimensional elements introduced physical depth into the graphic treatment and allowed branding to become part of the scenic construction.


    The wall graphics themselves were produced by an outsourced specialist supplier. Similarly, the printed fabric was outsourced rather than manufactured directly by Evolution Scenic. Evolution Scenic coordinated these specialist components with the workshop-built scenic package so that the printed surfaces and fabricated structures formed a consistent finished environment. This distinction is important when describing the project accurately. Evolution Scenic fabricated the physical scenic environment and logos while specialist suppliers produced the confirmed printed graphic and fabric components.


    The scenic walls provided the substrates, proportions and architectural framework into which these graphic treatments were installed. The result was a layered branded environment using several methods simultaneously. dimensional fabricated logos, PU-painted scenic surfaces, applied wall graphics and printed fabric treatments. Together, these elements created a stronger visual environment than graphics alone could have achieved.

    Evolution Scenic fabricated branded wall elements within the temporary Saudi Event Show lounge.

    Creating the Floating Fabric Ceiling


    The most visually distinctive part of the lounge was positioned overhead. Repeated blue fabric elements were suspended across the space using metal rods, creating a floating ceiling installation above the scenic walls and furniture. The individual pieces established a strong rhythm through the lounge and gave the temporary build a recognisable identity from several viewpoints within the exhibition hall.


    Unlike a solid scenic ceiling, the repeated fabric elements allowed the overhead treatment to remain visually lightweight. This was particularly suited to an exhibition environment where the structure needed to define the lounge without attempting to reproduce the construction of a permanent room. The ceiling also extended the blue graphic language vertically through the installation, connecting the overhead environment with the blue accents used around the seating and display areas.


    The confirmed construction information identifies fabric and metal rods. Printed fabric production was outsourced. The precise textile specification, rod sections, attachment details and suspension engineering are not available in the supplied project records and have therefore not been assumed. From a scenic perspective, the feature demonstrates how fabric can be used as an architectural material within temporary construction rather than simply as surface decoration.

    Blue suspended fabric installation defining the temporary SES Exhibition Lounge ceiling.

    SUSPENDED FABRIC CEILING FEATURE


    One of the defining scenic elements of the SES Exhibition Lounge was the suspended blue fabric ceiling treatment. The feature was constructed using fabric and metal rods, creating a repeated overhead composition above the lounge. Rather than installing a conventional solid scenic ceiling, the project used individual suspended fabric elements to create a lightweight architectural layer.


    This approach helped establish a strong visual boundary above the lounge while allowing the environment to remain open within the much larger volume of the RICEC exhibition hall. The repeated fabric forms introduced rhythm across the ceiling and helped visually connect different parts of the lounge beneath them. Their blue colour also provided contrast against the white scenic wall construction and reinforced the visual identity of the environment.


    The overhead installation demonstrates how fabric can be used as a three-dimensional scenic construction material rather than simply as a printed graphic surface. Supported by metal rods, the fabric became part of the spatial architecture of the lounge. The feature also helped give the environment a recognisable profile when viewed from different positions within the exhibition hall. The scenic identity was therefore established not only through the walls and furniture at floor level but also through the space above them.


    Printed fabric production was undertaken by an outsourced specialist supplier. The exact fabric specification, individual rod sizes, suspension points and fixing details have not been supplied. These technical details are therefore not presented as confirmed project information. From a scenic fabrication perspective, however, the feature demonstrates the importance of coordinating lightweight textile elements with fabricated architectural structures to create a complete temporary environment.

    Suspended blue fabric ceiling elements supported by metal rods above the exhibition lounge.

    TECHNICAL INTEGRATION, SITE INSTALLATION & VENUE PROTECTION


    The lounge incorporated integrated digital display screens supplied by Evolution Technical. The screens were strategically positioned throughout the environment to show exhibition information and provide an overview of Evolution's contribution as a sponsor.


    Rather than treating the screens as freestanding audiovisual equipment, they were visually incorporated into the scenic wall construction. This required coordination between the scenic and technical packages.


    The scenic walls needed to provide suitable locations and finished architectural surrounds for the screens, while the display technology needed to align accurately with the visible wall openings.

    Integrating technical equipment into scenic fabrication helps reduce visual clutter and allows screens to appear as intentional parts of the architecture. Once workshop fabrication was complete, the modular scenic elements were transported to the Riyadh International Convention & Exhibition Center for site installation.


    Because the principal components had already been manufactured as modular sections, the venue phase focused on assembling and aligning the scenic environment and integrating the remaining packages. The site installation brought together: scenic wall sections, custom joinery, dimensional logos, outsourced graphics, suspended fabric elements, furniture and technical displays.


    Floor protection was a confirmed venue requirement. This was particularly important during installation and dismantling because fabricated wall sections, metal components, tools, furniture and technical equipment needed to be moved through the exhibition space without damaging the existing venue surfaces.


    On temporary exhibition projects, installation would normally also require coordination between scenic, technical, furniture and venue teams so that each package can be introduced in a controlled sequence. This represents normal project methodology and is not presented as a confirmed detailed installation sequence for the SES Exhibition Lounge. The exact installation duration, crew numbers and access schedule have not been supplied separately from the confirmed 15-day overall programme.

    White modular scenic walls with integrated digital displays and custom exhibition seating.

    PROJECT DELIVERY, DISMANTLING & OUTCOME

    The SES Exhibition Lounge was delivered through a confirmed 15-day overall programme. Within that programme, Evolution Scenic manufactured and delivered a temporary environment combining several different areas of scenic production.


    The completed lounge incorporated modular PU-painted wall structures, custom joinery, bespoke standing tables, dimensional branding, graphic surfaces, integrated display technology, lounge furniture and the distinctive suspended fabric ceiling.


    What appeared as a simple and clean exhibition lounge was therefore the result of multiple coordinated fabrication and supply packages. The modular scenic walls established the architecture.


    The custom coffee bar and networking tables provided functional joinery. The suspended fabric installation defined the environment overhead. Dimensional logos and outsourced graphics provided branding.


    Evolution Furniture completed the seating areas. Evolution Technical integrated the digital display package. Together, these components created one connected temporary interior rather than a collection of independent exhibition products.


    The project also demonstrates the practical importance of designing scenic environments around their full lifecycle. Evolution Scenic was responsible not only for fabrication and installation but also for dismantling the lounge after the exhibition.


    The environment therefore needed to perform successfully during the Saudi Event Show while remaining suitable for controlled removal once the exhibition had finished.


    The final installation demonstrated Evolution Scenic's capabilities across scenic fabrication, modular exhibition construction, bespoke joinery, PU scenic finishing, dimensional branding, temporary architecture and technical integration.

    Evolution Scenic SES Lounge fabrication combining scenic walls, furniture and technical displays.
  • Make it in the Emirates Forum Scenic Fabrication, Abu Dhabi 2023

    Evolution Scenic main stage and integrated scenic architecture for Make it in the Emirates Abu Dhabi.

    Building a Unified Scenic Environment for Make it in the Emirates


    The second Make It in the Emirates Forum took place at Abu Dhabi Energy Centre from 31 May to 1 June 2023. The venue needed to accommodate a main conference stage, breakout presentation spaces, sponsor exhibition environments, arrival features, branded circulation routes and integrated technical displays within one connected event environment.


    Evolution Scenic was appointed to deliver the full turnkey scenic solution and developed the overall event concept before translating it into practical temporary architecture. The scope included the main stage, breakout stages, exhibition area, arrival arch, project flooring, scenic walls, branded portals, signage, wayfinding and integrated display structures.


    The exhibition layout was developed to accommodate six diamond sponsors and 30 additional sponsors. Each organisation needed its own visible and functional presence, while the wider environment still had to maintain a consistent architectural identity. Balancing individual sponsor requirements with the overall scenic concept became an important part of the design and fabrication approach.


    Rather than treating the project as a collection of unrelated stages, booths and branded structures, Evolution Scenic developed the venue as a single scenic system. Geometry, materials, graphics, screen integration and architectural detailing were repeated across different zones so that the environment remained visually connected from arrival through to the main conference and exhibition spaces.

    Developing a Consistent Architectural Language


    The scenic concept used a strong geometric language based around angled wall profiles, layered surfaces, framed openings and illuminated linear features. These details were repeated across the main stage, breakout spaces, sponsor structures, Government Hub, arrival environment and wayfinding features.


    The main conference stage established the principal architectural direction. A broad screen composition was surrounded by angular scenic architecture, while layered stage steps carried the same geometry into the floor. Branded vertical elements added another level of depth and connected the presentation area with the visual identity used throughout the venue.


    Breakout stages applied the same design principles on a smaller scale. Integrated screen openings, presentation plinths and scenic wall systems provided each space with the functionality required for individual sessions while maintaining a clear relationship with the primary conference stage.


    The exhibition environments extended this language into the sponsor areas through fabricated walls, overhead structures, counters and integrated display positions. The arrival arch introduced the same architectural character before visitors reached the main environment, using dynamic content and fabricated scenery to establish the project identity from the entrance onwards.

    Fabricating the Scenic Package


    MDF and plywood were the principal scenic materials used across the project. Their versatility allowed the workshop team to manufacture the controlled flat surfaces, angular profiles, arches, screen frames, stage features and exhibition structures required by the concept while maintaining consistent edges and junctions across the different areas.


    Selected elements combined metal framing with MDF cladding. The internal metal construction provided structural support where required, while the MDF faces created the smooth visible architectural surfaces used throughout the wider scenic scheme. This allowed individual structures to respond to different technical and functional requirements without changing the external design language.


    Evolution Scenic fabricated the project flooring, all scenic walls and arches and most of the other visible scenic elements. With multiple stages, sponsor environments, portals and presentation zones being manufactured as parts of one package, accurate set-out was essential to maintaining relationships between wall lines, floor transitions, overhead features, graphics and screen openings.


    Workshop production therefore played a central role in controlling the complete installation. Components needed to connect accurately once delivered to Abu Dhabi Energy Centre, while graphic zones, technical apertures and adjoining scenic structures had to maintain the proportions established during design development. Fabrication accuracy allowed the different parts of the project to come together as one consistent temporary architecture on site.

    Delivering the Forced-Perspective Feature


    Forced perspective formed part of the wider event concept and introduced a scenic feature that relied on controlled geometry rather than conventional flat construction. The feature was fabricated as two principal sections before being transported to Abu Dhabi Energy Centre and assembled in its final position.


    Dividing the structure into two sections made the feature practical to manufacture, handle and install while creating an important requirement at the connection between the two halves. Once assembled, the separate components needed to appear as one continuous scenic form rather than two independent fabricated sections.


    Forced-perspective environments depend on the relationship between line, scale, depth and the position from which the feature is viewed. Maintaining these relationships through the fabrication process meant the geometry of both sections needed to correspond accurately when brought together on site.


    The finished feature demonstrates how visually complex scenery can be broken into practical manufactured sections without losing the intended effect. It also illustrates the importance of considering transport, assembly and installation while developing unusual scenic forms rather than resolving those requirements only after fabrication has begun.

    Integrating Screens into the Scenic Construction


    The project incorporated an extensive technical display package across the main conference stage, breakout areas, Government Hub, sponsor environments and arrival architecture. One principal screen was supplied by Abu Dhabi Energy Centre, while the remaining screens were installed by Evolution Technical’s in-house team.


    The venue screen was incorporated into the main stage architecture rather than treated as an independent technical element. Scenic walls and stage geometry framed the display and connected it visually with the surrounding environment, allowing the screen to become part of the architectural composition of the stage.


    Additional screens were integrated into fabricated structures throughout the sponsor exhibition areas, Government Hub, breakout stages and presentation spaces. Screen positions needed to align with the scenic openings, while surrounding panels, trims and graphic surfaces created the finished architectural interface around each technical system.


    The arrival arch also incorporated dynamic content, extending the relationship between scenic fabrication and digital display into the visitor arrival sequence. This allowed the visual language established around the main stage technology to continue into a very different type of structure.


    Coordination between Evolution Scenic and Evolution Technical was particularly valuable at the interface between fabricated scenery and technical equipment. The technical systems required suitable support and operational access, while the scenic construction needed controlled edges, accurate openings and clean finishes. Developing both disciplines within the Evolution group allowed those interfaces to be treated as parts of the same built environment.

    Constructing the Sponsor Exhibition Environment


    he exhibition area was developed to accommodate six diamond sponsors and 30 additional sponsors within a shared architectural environment. The challenge was to provide individual organisations with clear presence and functional presentation space without allowing the exhibition floor to become a collection of visually unrelated stands.


    Fabricated wall structures, overhead branding elements, integrated monitors, meeting counters and presentation surfaces established the individual sponsor environments. Open frontages maintained visibility and circulation through the exhibition area, while scenic structures created enough architectural definition for each organisation to establish its own presence.


    Repeated details such as vertical fins, angled portals, illuminated edges and framed screen openings linked these individual areas back to the wider Make It in the Emirates identity. Sponsor graphics and digital content could vary within each space, while the physical construction retained the common geometry and material language established across the project.


    The Government Hub created one of the strongest individual environments within the exhibition. Vertical illuminated features, recessed screens and a central branded header defined the area, while its curved layout created a recognisable presentation zone without disconnecting it from the angular scenic language used elsewhere.


    By controlling the architecture centrally while allowing individual branding within it, Evolution Scenic was able to balance sponsor visibility with overall consistency. The result was an exhibition area in which individual identities remained clear while the physical environment continued to read as part of one event.

    Installing Within Abu Dhabi Energy Centre


    The scenic package was installed within the existing finished environment of Abu Dhabi Energy Centre. Protecting the venue formed an important part of the site operation, with protective measures applied to existing floors, walls and glazed surfaces during installation and subsequent dismantling.


    This was particularly important given the physical extent of the project. Large scenic wall assemblies, project flooring, arches, stages, display structures and numerous sponsor environments all needed to be transported through the venue, positioned and assembled without damaging the surrounding architectural finishes.


    Evolution Scenic installed the project flooring, all scenic walls and arches and most of the additional scenic elements. The two-part forced-perspective structure was assembled on site, while the main stage and exhibition environments were coordinated with both the existing venue screen and the additional display systems installed by Evolution Technical.


    The scenic installation also had to respond accurately to fixed conditions within the building. Existing architecture, usable floor areas, circulation routes and technical infrastructure established physical boundaries around which the temporary environment had to be positioned.


    Bringing the project together required careful coordination between flooring, large scenic structures, sponsor zones, screens, graphic finishes and supporting branded elements. The installation translated a substantial workshop-built package into the final venue environment while maintaining the consistent geometry and finish developed through the scenic concept.

    Completing and Removing the Temporary Environment


    Once installed, the scenic package transformed Abu Dhabi Energy Centre into a connected series of branded temporary environments. The main conference stage, breakout stages, sponsor exhibition areas, Government Hub, arrival feature and wayfinding structures all performed different functions while sharing the same architectural vocabulary.


    Integrated display systems became part of the physical architecture rather than sitting independently within it. Screens were framed within scenic walls and sponsor structures, while the arrival arch combined fabricated form with dynamic content. MDF, plywood and selected metal-framed construction allowed these different elements to maintain a consistent external finish despite their varied structural and technical requirements.


    The sponsor exhibition environment demonstrated the same approach at a larger scale. Six diamond sponsors and 30 additional sponsors were accommodated within individual settings while the repeated geometry, framing and illuminated detailing maintained visual consistency across the complete floor.


    Following the forum, Evolution Scenic dismantled the temporary installation, completing a scope that extended from concept development and fabrication through installation and final removal. Venue protection remained part of this process as the scenic structures, flooring and technical interfaces were taken out of the finished building.


    Make It in the Emirates demonstrates Evolution Scenic’s ability to manage a substantial multi-zone scenic package combining conference staging, exhibition fabrication, sponsor environments, temporary architecture, branding and technical integration. By developing the physical environment and coordinating closely with Evolution Technical, the project could operate as one complete scenic system rather than a collection of independent production elements.

  • Qudwa–PISA Forum Scenic Fabrication at Expo 2020 Dubai

    Evolution Scenic modular Qudwa–PISA stage and LED surrounds at Expo 2020 Dubai.

    Building a Modular Forum Environment at Expo 2020 Dubai


    The Qudwa–PISA Global Competence Forum took place at Expo 2020 Dubai on 19 February 2022. Developed around the theme Preparing Students to Live in an Interconnected World, the forum was delivered in collaboration with the OECD and the Bussola Institute.


    Evolution Scenic was responsible for developing and delivering the physical scenic environment. The scope extended well beyond the main presentation area and included the stage deck, screen structures, Media Hub installation, partitions, branded backdrops, illuminated totems and plinths, signage, wayfinding and lounge elements.


    Each part of the environment performed a different function, but the complete installation needed to operate as one coordinated piece of temporary architecture. This required the stage, technical displays, exhibition structures, branding and supporting elements to share a consistent architectural and graphic language throughout the forum.

    Developing the Scenic Concept


    Evolution Scenic developed the scenic design rather than working solely from a completed third-party production package. This allowed the visual concept, fabrication methodology, material choices and installation requirements to be considered together from the beginning of the project.


    The forum identity was translated into a combination of solid scenic surfaces, framed technical displays, illuminated vertical elements and areas of coloured transparency. The main stage established the strongest architectural expression, with the same visual principles subsequently carried into the Media Hub, partitions, branded structures and wayfinding elements.


    Maintaining this continuity was particularly important because the forum contained several distinct functional areas. Consistent proportions, framing, materials and graphics allowed each zone to retain its own purpose while still reading as part of the same temporary environment.

    Constructing the Main Stage


    The main stage and stage deck formed the central scenic structure within the forum. Evolution Scenic fabricated the physical stage environment, including the deck, surrounding scenic architecture and the metalwork required to integrate the LED screens supplied by Evolution Technical.


    MDF, plywood and timber framing formed part of the confirmed material palette. These materials provided adaptable scenic surfaces that could be produced in modular sections and finished with the required graphics and decorative treatments, while metal framing provided additional structural support around the technical display systems.


    The screens were treated as integral parts of the stage composition rather than freestanding pieces of equipment. Their positions influenced the proportions of the surrounding architecture, while the fabricated scenic elements established the visual boundaries that connected the displays to the wider stage.


    The stage also needed to support practical technical operation. Scenic surrounds were therefore developed around the physical requirements of the screens and their supporting systems, allowing the visible architecture and technical installation to work together as one coordinated environment.

    Integrating the LED Systems


    Evolution Technical supplied the LED screen systems used within the main stage. Evolution Scenic fabricated the metal structures and scenic surrounds that incorporated those displays into the architecture of the presentation environment.


    This required accurate coordination between the dimensions of the technical equipment and the fabricated scenic components. Screen position influenced the spacing, alignment and overall geometry of the surrounding structures, while the scenic architecture determined how the technical equipment was visually framed from the audience position.


    The resulting stage combined two connected disciplines. Evolution Scenic created the physical architecture, while Evolution Technical delivered the display systems operating within it, allowing structural, scenic and technical elements to appear as parts of one resolved composition.


    The same collaborative approach extended beyond the main auditorium into the Media Hub, where fabricated frames, graphics and technical displays again needed to operate within a shared architectural system.

    Fabricating the Media Hub


    The Media Hub was developed as a freestanding scenic feature within the wider forum environment. Evolution Scenic fabricated metal-framed panels incorporating coloured transparent sheet and printed graphics, creating a distinct secondary zone without requiring permanent modification to the Expo venue.


    The metal frames established the geometry and structural definition of the feature, while the transparent coloured materials introduced layering and visual depth. Unlike solid scenic walls, these surfaces allowed parts of the surrounding environment and structural framing to remain visible, creating a lighter architectural treatment.


    Printed graphics were incorporated within the framed composition to connect the Media Hub visually with the wider Qudwa–PISA identity. The relationship between structural frames, transparent panels and graphic surfaces allowed the installation to remain distinctive without feeling disconnected from the main stage environment.


    Evolution Technical supplied the display equipment incorporated into the Media Hub. The scenic framing was therefore developed around the technical components so that screens, coloured materials and printed graphics aligned as one coordinated installation.

    Producing Partitions and Branded Backdrops


    Custom partitions and branded backdrops were fabricated to define different areas throughout the forum. These elements functioned as temporary spatial architecture, providing visual separation, branded surfaces and controlled backgrounds without becoming permanent interventions within the Expo venue.


    The confirmed construction palette included MDF, plywood, timber framing, metal framing, acrylic, printed fabric and vinyl graphics. Timber-framed panel construction allowed the larger elements to be manufactured as modular sections, while MDF and plywood provided smooth surfaces suitable for consistent graphic and decorative finishes.


    Metal framing was incorporated where freestanding structures required additional support or where the construction needed to relate visually to the screen surrounds and Media Hub. This created continuity between the heavier scenic walling and the lighter framed structures positioned elsewhere within the environment.


    Together, the partitions and backdrops extended the architectural language beyond the main stage. They helped organise the venue spatially while providing a consistent physical framework for branding, interpretation and circulation.

    Branded Totems, Plinths, Signage and Reception Counters


    Evolution Scenic fabricated MDF totems and plinths finished with vinyl graphics to create smaller branded focal points throughout the forum. These elements extended the visual identity into areas where a full scenic wall or large architectural installation was unnecessary.


    Reception counters, signage and wayfinding used the same coordinated approach to graphics, proportions and finishes. Their scale was smaller than the principal scenic structures, but their positioning and appearance were important to maintaining continuity through the visitor journey.


    The freestanding nature of these elements allowed them to be placed according to the practical needs of each area while remaining visually connected to the wider environment. Their finishes and graphic treatment ensured that supporting functions such as reception, information and navigation became part of the overall scenic language.


    By carrying the design into these smaller components, the temporary architecture extended beyond the main visual moments. The complete forum environment could therefore maintain a consistent identity from the principal stage through to the supporting circulation and reception areas.

    Creating Lounge and Seating Areas


    Evolution Scenic fabricated MDF totems and plinths finished with vinyl graphics to create smaller branded focal points throughout the forum. These elements extended the visual identity into areas where a full scenic wall or large architectural installation was unnecessary.


    Reception counters, signage and wayfinding used the same coordinated approach to graphics, proportions and finishes. Their scale was smaller than the principal scenic structures, but their positioning and appearance were important to maintaining continuity through the visitor journey.


    The freestanding nature of these elements allowed them to be placed according to the practical needs of each area while remaining visually connected to the wider environment. Their finishes and graphic treatment ensured that supporting functions such as reception, information and navigation became part of the overall scenic language.


    By carrying the design into these smaller components, the temporary architecture extended beyond the main visual moments. The complete forum environment could therefore maintain a consistent identity from the principal stage through to the supporting circulation and reception areas.


    Coordinating Externally Supplied Banners


    Tall floor-supported graphic banners were produced by an external specialist supplier and incorporated into the wider forum layout. Evolution Scenic coordinated these elements alongside its fabricated stage, partitions, framed displays and branded structures.


    Maintaining a clear distinction between packages was important. The banners formed part of the final visual environment but were not manufactured by Evolution Scenic, while the surrounding scenic architecture and fabricated elements remained within Evolution Scenic’s direct production scope.


    The positioning of the banners still needed to respond to the scale and layout of the scenic installation. Their graphic presence contributed to the wider visual identity and therefore needed to sit comfortably alongside the dimensional structures, screens and branded surfaces developed elsewhere in the venue.


    Large temporary environments frequently involve several specialist contractors working together. The Qudwa–PISA environment demonstrates how externally supplied elements can be incorporated into a coordinated scenic scheme while retaining clear responsibility for individual fabrication packages.

    Modular Workshop Fabrication


    The complete scenic environment was produced in modular sections, allowing the main stage structures, framed panels, partitions and backdrops to be manufactured away from the venue under controlled workshop conditions.


    Modular construction made the larger elements more manageable for transportation and load-in. Instead of moving complete full-scale structures, the fabrication team could prepare controlled sections that were transported separately and assembled in their final positions at Expo 2020 Dubai.


    This approach placed particular importance on workshop accuracy. Connections needed to align consistently, framed structures had to remain square and graphic surfaces needed to meet cleanly once individual modules were joined together on site.


    The stage surrounds also had to correspond accurately with the dimensions and positions of the technical displays. Completing this coordination during fabrication reduced the amount of adjustment required within the venue and supported a more controlled installation process.

    Completing the Two-Day Installation


    The complete on-site scenic installation was delivered over two days. Modular construction and detailed workshop preparation allowed a substantial proportion of the physical production to be completed before the scenic package arrived at Expo 2020 Dubai.


    The stage deck and modular scenic sections were assembled before the fabricated surrounds were coordinated with the LED screens supplied by Evolution Technical. The relationship between the screens and scenic architecture could then be checked as the primary presentation environment came together.


    The Media Hub was installed as a separate scenic feature, combining its metal frames, coloured transparent panels, printed graphics and technical displays. Partitions, branded backdrops, illuminated totems, plinths, reception elements, signage, wayfinding and lounge structures were positioned across the wider forum environment.


    Externally supplied graphic banners were also incorporated into the final layout. Delivering multiple zones within the two-day installation required a controlled sequence so that structural assembly, technical installation, graphics and final scenic finishing could progress efficiently alongside one another.

    Creating a Unified Temporary Environment


    The completed Qudwa–PISA Global Competence Forum brought scenic fabrication, technical integration and temporary architecture together within one coordinated environment. The main stage combined a modular deck, fabricated scenic structures, metal screen surrounds and LED displays to create the principal presentation setting.


    The Media Hub introduced a different architectural character through freestanding metal frames, coloured transparent materials, printed graphics and integrated technical displays. Partitions and backdrops established the surrounding spatial structure, while illuminated totems, plinths, signage and wayfinding extended the visual identity throughout the venue.


    Lounge and reception elements brought the same design approach into the functional areas supporting the main programme. Externally supplied banners were coordinated within the overall layout, allowing specialist packages to contribute to the completed environment without blurring responsibility for their manufacture.


    Following the forum, the installation was dismantled. From initial scenic development through workshop fabrication, technical coordination, two-day installation and final removal, the project demonstrates the operational value of connecting scenic and technical disciplines within one temporary architectural system. Evolution Scenic produced the physical environment while Evolution Technical supplied the integrated LED and Media Hub systems, with both disciplines coordinated as parts of the same finished space.

  • Forever Valentino Exhibition Scenic Fabrication at M7 Doha

    Structural steel fabrication integrated into the Forever Valentino exhibition architecture.

    Engineering An Immersive Exhibition Environment


    The Forever Valentino Exhibition at M7 Doha transformed a contemporary gallery into a sequence of immersive architectural spaces celebrating the heritage of Maison Valentino. Working alongside Kennedy London, Evolution Scenic was responsible for the technical development of the exhibition, including fabrication drawings, engineering calculations, scenic manufacturing and on-site installation.


    The project required far more than the construction of conventional exhibition displays. The creative direction drew heavily on the architectural character of Rome, using monumental scenic structures, sculptural reproductions, specialist display elements and immersive environments to frame different moments within Valentino’s history.


    Each gallery introduced a distinct spatial experience, requiring bespoke fabrication rather than a repeated modular system. The scenic architecture therefore became part of the storytelling itself, with every structure developed to support both the exhibition narrative and the museum-quality presentation expected within M7 Doha.

    Translating Creative Design Into Fabricated Reality


    One of the defining challenges was converting highly detailed conceptual designs into scenic structures that could be engineered, manufactured, transported and installed without weakening the architectural intent. Evolution Scenic developed the creative scheme into coordinated fabrication information, allowing each gallery environment to progress from concept into practical workshop production.


    The exhibition incorporated architectural references to Rome alongside sculptural and display elements associated with different chapters of Valentino’s history. Among the most prominent features was a large-scale Colosseum-inspired scenic structure, supported by additional architectural environments, bespoke display elements and a recreation of a classical statue.


    Unlike a conventional exhibition where the displays sit independently from the surrounding space, the scenic construction formed an active part of the visitor journey. Walls, structures, furniture and sculptural features helped establish the character of each gallery and created the architectural context in which the collection was presented.


    This approach required close coordination between technical design, engineering and fabrication. Each bespoke structure needed to remain practical to manufacture in the UAE, transport internationally and assemble accurately within the galleries while maintaining the refined appearance established by Kennedy London’s design.

    Engineering Monumental Scenic Structures


    The exhibition required a wide range of construction methods, from precision scenic joinery and architectural walling to substantial structural steel fabrication. Each element was engineered around its own scale, form and role within the exhibition while remaining visually connected to the wider architectural language.


    One of the principal engineered installations was the Gasometer-inspired steel structure. This feature required significant structural fabrication while retaining a finish suitable for a luxury cultural exhibition, demonstrating the need to balance engineering performance with close-range visual presentation.


    Elsewhere, bespoke scenic environments combined structural framing, architectural detailing, display furniture and sculptural components. These elements were not treated as independent construction packages but as parts of a complete gallery composition in which proportions, finishes and interfaces needed to remain controlled.


    Because visitors experienced the work at close proximity, engineering accuracy alone was not enough. Fabrication tolerances, surface alignment, joinery details and finished edges all contributed directly to the visual quality of the exhibition, requiring structural and scenic disciplines to operate together throughout production.

    Materials, Scenic Craftsmanship and Museum-Quality Finishes


    The confirmed construction scope combined structural steelwork, timber construction and specialist scenic fabrication. These disciplines allowed Evolution Scenic to produce both monumental architectural elements and more finely detailed exhibition components within the same project, supporting the varied scale of the gallery environments.


    Steel fabrication provided the structural basis for major installations such as the Gasometer-inspired feature, while timber construction and scenic joinery were used throughout the architectural walling, custom display furniture and smaller exhibition structures. Sculptural reproductions and detailed scenic elements added another layer of fabrication to the overall environment.


    The close viewing distances within the galleries placed particular importance on finish quality. Surfaces needed to remain consistent, joints had to be carefully resolved and architectural details required crisp, controlled fabrication so that the physical construction could withstand the level of scrutiny expected within an international exhibition.


    This balance between structural performance and scenic craftsmanship allowed large engineered forms and delicate presentation elements to coexist within the same visual language. The result was an exhibition environment in which the technical complexity of the construction remained concealed behind refined architectural surfaces.

    International Fabrication and Logistics


    The complete scenic package was manufactured in the United Arab Emirates before being transported to Doha for installation at M7. This added an important logistical dimension to the project because every bespoke component needed to leave the workshop prepared for international transport and subsequent installation within a cultural venue.


    Many of the structures were unique architectural elements rather than interchangeable exhibition components. Large steel fabrications, scenic assemblies, sculptural pieces and specialist display structures therefore required careful handling to protect both their structural integrity and their completed finishes during transportation.


    Fabrication decisions had to consider the journey from workshop to site as well as the final installed appearance. The way individual structures divided, the size of transportable sections and the protection of finished surfaces all influenced how the scenic package could move efficiently from the UAE to Qatar.


    International delivery therefore became part of the wider technical development process rather than a separate activity after fabrication. The project required manufacturing, engineering, logistics and installation to remain coordinated so that bespoke scenic elements could arrive ready to be assembled accurately within the gallery sequence.

    Installing the Exhibition at M7 Doha


    Installation at M7 Doha required numerous bespoke scenic environments to be assembled and aligned within the existing gallery architecture. Each component needed to correspond accurately with the planned exhibition layout while maintaining the visual sequence established by Kennedy London’s creative design.


    Large structural features established the primary architectural framework before the surrounding scenic elements, display structures and sculptural pieces were completed around them. This created a staged installation process in which the principal structures provided the reference points for the more detailed scenic and display components.


    Dimensional coordination remained particularly important because each gallery contained unique fabricated elements. Adjacent scenery, architectural features and display structures needed to align accurately so that joints, transitions and spatial relationships appeared deliberate rather than the result of separate construction packages.


    The completed installation brought together large-scale engineering and detailed scenic craftsmanship within one controlled gallery environment. Accuracy during site assembly was essential to preserving the quality established in the workshop and ensuring that the architecture maintained the refined finish expected of a luxury fashion exhibition.

    Creating an Immersive Architectural Journey


    The success of the Forever Valentino Exhibition depended on how the individual gallery environments worked together as a complete journey. Each space introduced a different chapter of Valentino’s story through architecture, sculpture, display furniture and scenic construction rather than relying solely on objects or graphic interpretation.


    Monumental scenic features created moments of architectural scale, while more detailed environments framed individual displays and collection pieces. The Colosseum-inspired structure, Gasometer-inspired steel installation, classical sculptural recreation and bespoke exhibition elements each contributed a different layer to the visitor experience.


    Although the galleries were individually designed, they shared a common fabrication philosophy. Structural engineering, scenic manufacturing, precise detailing and controlled installation were used consistently across the project, allowing the visitor to move between different environments without losing the wider architectural coherence of the exhibition.


    The close relationship between architecture and exhibition content allowed the scenery itself to become part of the interpretation. Rather than functioning as a neutral backdrop, the fabricated environments created the context through which Valentino’s history, design language and connection to Rome could be experienced.

    Delivering a Complex International Exhibition


    The completed Forever Valentino Exhibition established a series of bespoke scenic environments combining architectural inspiration, structural engineering and museum-quality fabrication within M7 Doha. Evolution Scenic delivered the technical development, fabrication drawings, engineering calculations, scenic manufacturing and installation required to realise Kennedy London’s design.


    The project brought together substantial steelwork, timber construction, scenic joinery, sculptural fabrication and specialist exhibition elements across multiple unique gallery spaces. Each construction discipline contributed to the same visitor experience, from monumental architectural features through to carefully detailed display structures and finishes.


    Manufacturing the complete scenic package in the UAE and installing it in Qatar added another layer of coordination, requiring fabrication, logistics and site assembly to remain connected throughout delivery. The project demonstrated Evolution Scenic’s ability to manage complex international exhibition environments where engineering, architectural detailing and presentation quality are equally important.


    Forever Valentino also illustrates how scenic fabrication can move beyond conventional event construction and operate within a museum-standard cultural environment. By combining technical development, engineered structures, bespoke manufacturing and precise installation, Evolution Scenic helped transform a creative exhibition concept into a sequence of immersive architectural spaces.

  • Global Citizen Forum Scenic Fabrication and Branded Environments in Ras Al Khaimah

    Evolution Scenic conference stage and branded scenic walling for Global Citizen Forum Ras Al Khaimah.

    Creating a Multi-Area Scenic Environment for the Global Citizen Forum


    The Global Citizen Forum took place at Al Hamra International Exhibition & Conference Centre in Ras Al Khaimah in 2021. Developed around the theme The Future in Motion, the programme included a two-day conference followed by a Gala Dinner, requiring several distinct areas of the venue to operate as parts of one connected visual environment.


    Evolution Scenic was appointed to provide scenic design, fabrication and event branding across the venue. Developing the scenic design alongside the fabrication scope allowed the visual concept, construction methodology, materials and installation requirements to be considered together rather than treating production as a separate stage after the design had been completed.


    The scope extended well beyond a conventional conference backdrop. It included the main stage environment, entrance architecture, exhibition displays, branded perimeter walling, presentation plinths, podiums and dedicated Gala Dinner scenery. Each area served a different function, but the complete project was developed through a consistent architectural, material and graphic language.

    Building the Main Conference Stage


    The main conference stage formed the principal architectural element within the auditorium. Evolution Scenic fabricated the complete stage deck and access steps together with black scenic walling, a branded lower fascia and custom podiums, creating a controlled visual setting around the principal presentation area.


    The venue’s existing LED screen established a fixed technical reference for the scenic construction. The surrounding walling, stage deck and fascia therefore needed to be developed around the position and proportions of the installed display so that the complete elevation appeared balanced from the main audience viewing positions.


    Black scenic surfaces created a restrained architectural frame around the screen content, while the branded fascia concealed the supporting stage structure and created a continuous graphic surface across the front elevation. The access steps and custom podiums followed the same construction and finish language, allowing the functional elements of the stage to read as parts of one coordinated environment.

    Integrating Scenic Construction with Venue Technology


    Working around a venue-owned LED screen required the scenic architecture to respond precisely to an existing technical installation. The screen needed to remain fully visible and operational while the surrounding walling provided a clean architectural frame that visually connected it with the stage deck and the wider conference environment.


    The scenic walls could not be positioned independently of the display. Their dimensions, base positions and finished edges needed to correspond with the installed screen, while the stage deck and front fascia had to maintain a consistent relationship with its lower edge. Accurate fabrication and positioning were particularly important across the wide stage elevation, where small dimensional differences would have been visually apparent.


    This coordination allowed the technical system to sit naturally within the scenic architecture rather than appearing as equipment placed against a temporary backdrop. The stage structure completed the visual composition while maintaining the separation required between the venue technology and Evolution Scenic’s fabricated scope.

    Extending the Identity Beyond the Auditorium


    The scenic environment continued beyond the principal conference stage into the arrival and exhibition areas. Evolution Scenic fabricated a large branded perimeter wall that established a defined architectural boundary within the venue and provided a substantial surface through which the Global Citizen Forum identity could extend into the wider space.


    A circular illuminated entrance feature introduced a stronger three-dimensional arrival point. Its curved geometry contrasted with the predominantly rectilinear walling and display structures used elsewhere, while integrated illumination reinforced its outline and made the feature clearly visible within the larger exhibition environment.


    Combining large-format walling with the illuminated entrance prevented the arrival area from becoming a sequence of flat graphic surfaces. The architectural wall established scale and enclosure, while the circular feature created a recognisable focal point that helped establish the transition into the forum environment.

    Fabricating Geometric Displays and Exhibition Features


    Evolution Scenic fabricated geometric metal-framed displays, freestanding exhibition panels and presentation plinths for the exhibition area. The open metal structures introduced a lighter architectural language than the solid perimeter walling, allowing objects and graphic content to be framed while maintaining visual depth through the surrounding space.


    Freestanding panels provided additional surfaces for information and branding and could be positioned according to the layout of the exhibition environment. Presentation plinths created elevated bases for individual objects, with their proportions and surface treatments developed to complement the wider material and graphic language rather than function as unrelated display furniture.


    Together, the perimeter wall, illuminated circular entrance, geometric frames, exhibition panels and plinths created a layered hierarchy of scenic elements. Larger architectural forms defined the overall space, three-dimensional features created focal points and smaller structures supported individual presentation moments, giving the exhibition area greater depth and visual organisation.

    Constructing the Gala Dinner Environment


    The Gala Dinner required a distinct scenic treatment while remaining connected to the wider visual identity of the Global Citizen Forum. Evolution Scenic fabricated a dedicated branded stage for the evening setting together with a globe feature and a gold-framed presentation plinth.


    The globe introduced a clearly sculptural object into an environment otherwise dominated by rectilinear stage, wall and display construction. Its curved three-dimensional form created a focal point within the room and provided a visual counterpoint to the more architectural scenic elements used throughout the conference and exhibition spaces.


    The gold-framed plinth added another dedicated presentation feature and introduced a different material character appropriate to the evening environment. Together, the stage, globe and presentation structure gave the Gala Dinner its own identity while retaining enough visual continuity for the space to feel like an extension of the wider forum rather than a separate project.

    Coordinating Graphics with Fabrication


    Branding formed part of the physical construction throughout the project rather than being treated as a final decorative layer. The stage fascia, scenic walling, exhibition panels, podiums and presentation plinths were all developed as fabricated surfaces that also carried the visual identity of the Global Citizen Forum.


    This required the dimensions of each scenic element to remain coordinated with the graphic layouts applied to it. Logos, text and visual motifs needed to sit correctly within the available surfaces and maintain alignment around edges, joints and adjoining components, particularly across larger scenic walls and the continuous front fascia of the main stage.


    The relationship between structure and graphics created consistency across areas that performed very different functions. The black stage architecture provided a controlled frame around the technical content, while the entrance and exhibition spaces combined larger branded surfaces with illuminated and three-dimensional forms. Fabrication established the physical hierarchy, and the graphic treatment connected those elements through one shared identity.

    Installing Multiple Scenic Zones


    Installation at Al Hamra International Exhibition & Conference Centre involved several distinct scenic zones. Within the auditorium, the stage deck, access steps, black scenic walls, fascia and podiums needed to be positioned accurately around the venue LED screen so that the completed stage maintained the proportions established during design development.


    The entrance and exhibition areas required a different installation sequence, bringing together the large perimeter wall, illuminated circular entrance, metal-framed displays, freestanding panels and presentation plinths. These structures varied considerably in size and construction but needed to maintain consistent alignment, finish quality and branding once positioned within the wider environment.


    The Gala Dinner stage, globe feature and gold-framed presentation element created an additional installation zone with its own spatial requirements. Coordinating these separate areas as parts of the same scenic package allowed the venue to transition between conference, exhibition and evening functions while maintaining a recognisable project identity throughout.

    Delivering a Consistent Temporary Architecture


    The completed Global Citizen Forum transformed several areas of the venue through purpose-built temporary scenic construction. The auditorium gained a complete architectural stage environment centred around the existing LED screen, while the arrival and exhibition areas were shaped through branded walling, illuminated entrance architecture, geometric displays and freestanding presentation structures.


    The Gala Dinner extended the project into a different setting through its dedicated stage, sculptural globe and gold-framed plinth. Although every area had its own functional requirements, the use of coordinated form, materials, graphics and fabrication methods allowed the individual environments to remain visually connected.


    Evolution Scenic’s combined design and fabrication scope allowed stage construction, scenic architecture, graphics, metalwork, feature fabrication and installation to develop as parts of one coordinated process. The finished project demonstrates how multiple temporary conference environments can be given a clear architectural identity through disciplined scenic design and fabrication rather than relying on branding alone.

  • UAE Regional Climate Dialogue Scenic Fabrication at Emirates Palace

    Evolution Scenic branded stage and angled graphic walls for the UAE Regional Climate Dialogue.

    Fabricating the UAE Regional Climate Dialogue environment at Emirates Palace


    The UAE Regional Climate Dialogue took place at Emirates Palace in Abu Dhabi in April 2021. The conference required a complete branded environment capable of supporting both physical and remote participation, with the scenic package creating a strong architectural setting within the room while accommodating the technical displays required for the hybrid format.


    Working from a supplied design, Evolution Scenic was responsible for fabricating and installing the principal scenic elements. The confirmed scope included the main stage deck and steps, central screen surround, large angled graphic walls, a freestanding photo-op backdrop, dimensional lettering, flags, signage and wayfinding. Evolution Technical supplied the displays incorporated into the main stage and photo-op installations.


    The complete fabrication and installation programme was delivered within one week, creating a significant fast-track challenge across technical development, workshop production, graphics, scenic finishing and site delivery. The scenic installation at Emirates Palace was undertaken overnight, making accurate preparation and coordination before load-in particularly important.

    Developing the Scenic Architecture


    Evolution Scenic translated the supplied visual design into a coordinated package of fabricated structures, finished surfaces and technical interfaces. The main stage deck and access steps created the functional raised presentation area, while the central backdrop, angled graphic walls and supporting branded structures established the wider architectural composition within the conference space.


    The stage deck, steps and front-facing scenic treatments were fabricated using materials from the confirmed project palette, including MDF, plywood and internal framing. These materials provided the defined profiles and smooth finished surfaces required for the graphic and vinyl treatments while allowing the structure to be manufactured efficiently within the compressed programme.


    The stage was developed as part of the complete scenic environment rather than as an isolated platform. Its geometry, fascia, finishes and adjoining elements needed to align visually with the central screen surround and surrounding scenic structures. With only one week available for fabrication and installation, buildability and workshop preparation were central to turning the supplied design into a practical installation.

    Integrating the Stage and Screen


    The central screen formed one of the principal visual elements within the main stage environment. Evolution Technical supplied the display, while Evolution Scenic fabricated the surrounding scenic architecture and branded backdrop, requiring accurate coordination between the screen position, fabricated opening and finished scenic edges.


    The surrounding structure created a deliberate architectural frame around the technical display. Graphic panels and branded surfaces connected the screen visually with the stage deck, fascia and wider scenic composition, allowing the technical equipment to sit naturally within the temporary architecture rather than appearing as a separate element placed against the scenery.


    Accurate workshop set-out was particularly important because even small differences between the display position and fabricated opening could affect the appearance of the completed backdrop. Coordinating the scenic and technical requirements during fabrication allowed the screen, structure and branding to come together as a single resolved presentation environment when installed on site.

    Extending the Scenic Environment


    Large angled graphic walls extended along both sides of the conference space, carrying the event identity beyond the central stage and increasing the physical scale of the scenic installation. Their changing geometry created greater depth than a conventional flat perimeter backdrop and helped connect the principal presentation area with the wider Emirates Palace interior.


    Evolution Scenic fabricated the wall system using materials from the confirmed project palette, including timber and metal framing, MDF, plywood, printed panels and vinyl graphics. Accurate workshop set-out was required so that individual sections maintained the supplied angles and connected correctly when assembled within the venue.


    The large-format graphics also needed to continue cleanly across the changing wall planes. Careful positioning and alignment of adjoining sections helped maintain visual continuity across the installation and reduced unnecessary breaks within the overall composition. Together, the angled walls acted as an architectural extension of the central stage and established a consistent branded environment throughout the room.

    Creating the Branded Support Elements


    Evolution Scenic also fabricated a separate freestanding photo-op backdrop incorporating printed graphics and a display supplied by Evolution Technical. The scenic framing, finished faces and technical opening needed to be developed as one coordinated structure so that the screen could be integrated cleanly without compromising the appearance of the branded backdrop.


    The freestanding construction allowed the feature to operate independently from the existing venue walls while retaining the alignment and finish required for photography and interview use. Its construction therefore had to provide both the necessary stability and the clean front-facing appearance expected from a highly visible branded feature.


    Dimensional lettering or hashtag elements positioned across the front of the main stage introduced additional depth to the branding and strengthened the visual connection between the stage and backdrop. Flags, signage and wayfinding extended the same graphic identity into the supporting areas, allowing smaller scenic elements to reinforce the visual language established by the principal structures.

    Fast-Track Fabrication and Overnight Installation


    The entire scenic package was fabricated and installed within one week. The programme covered the production of several large scenic structures, integrated technical interfaces, printed and applied graphics, dimensional branding and supporting elements, placing significant importance on accurate workshop coordination and preparation before the project reached site.


    Installation at Emirates Palace was undertaken overnight. The available working period needed to accommodate positioning the stage deck, installing the steps and fascia, assembling the screen surround, installing the angled graphic walls and positioning the freestanding photo-op structure. Each part of the environment had to be completed in a sequence that allowed the adjoining scenic and technical elements to follow efficiently.


    Evolution Technical’s displays also needed to be installed and accurately aligned with the fabricated scenic openings before the final dimensional lettering, flags, signage and wayfinding were positioned. The compressed programme demonstrates the importance of completing as much coordination, fabrication and checking as possible within the workshop before a scenic package enters a restricted overnight installation window.

    Delivering a Complete Temporary Conference Environment


    The finished UAE Regional Climate Dialogue environment brought stage construction, framed scenic walls, printed branding, dimensional lettering and technical displays together within one coordinated installation. The main stage established the architectural focus of the conference space, while the angled graphic walls extended the visual identity across the room and increased the perceived scale of the scenic environment.


    The freestanding photo-op created an additional branded setting incorporating its own technical display, while dimensional lettering, flags, signage and wayfinding extended the same design language through the supporting areas. Although these elements varied considerably in scale and construction, they formed part of the same coordinated scenic package and needed to maintain a consistent standard of fabrication and finish.


    Evolution Scenic’s role centred on translating the supplied design into a practical fabrication and installation system. Coordinating the scenic construction with Evolution Technical’s display requirements from the beginning allowed screens, branded surfaces and structural elements to operate within the same visual framework. Delivered within one week and installed overnight at Emirates Palace, the project demonstrates how technical coordination, workshop preparation and buildability can support fast-track scenic delivery for a hybrid conference environment.