• ADEO EC Retreat Interactive Scenic Fabrication in Abu Dhabi

    Coordinated ADEO scenic installation combining MDF walls, acrylic displays and printed graphics.

    Engineering the Interactive Scenic Environment


    The ADEO EC Retreat TP took place in Abu Dhabi in 2025, with Evolution Scenic delivering the complete fabrication and installation of the interactive scenic environment. The project comprised a coordinated series of freestanding workshop walls, participant engagement features and tinted-acrylic display structures. Each element was developed around a specific workshop function, including strategic discussion, voting, idea development, mapping and participant feedback.


    To create consistency across the different installations, Evolution Scenic developed a common structural methodology for the freestanding scenic walls. Each unit incorporated a timber-framed internal structure positioned on a plywood base and finished with MDF cladding to create smooth architectural surfaces for paint and printed vinyl application.


    The lower sections of the walls incorporated concealed counterweight supports, allowing the structures to remain stable without permanent fixing to the existing venue architecture. Removable rear access panels were integrated into the base areas so the counterweight zones could be reached during positioning, installation and final adjustment.


    This repeatable structural system created a reliable technical foundation across the project while allowing each wall to adopt its own scale, graphic treatment and interactive components. By maintaining a shared construction language throughout the installation, the different workshop features could operate as individual engagement tools while still reading as part of one coordinated temporary scenic environment.

    Fabricating the Answer, Voting and Ideation Walls


    The Write Your Answer Wall, Voting Wall and Ideation Wall were developed using the same principal freestanding scenic construction methodology. Each structure incorporated a timber-framed internal support system mounted on a plywood base and finished with MDF cladding. The MDF provided a clean, continuous surface across the participant-facing elevations while also creating a suitable substrate for the applied graphic finishes.


    Printed vinyl graphics were applied to the visible wall faces according to the individual workshop layouts. This allowed each installation to perform a different engagement function while maintaining the same construction quality and visual consistency.


    The Write Your Answer Wall provided a dedicated surface for participant responses, while the Voting Wall and Ideation Wall were organised around their respective workshop activities.

    Behind the finished surfaces, the timber framing, counterweight supports and structural interfaces remained concealed within the scenic assembly.


    Removable rear access panels allowed the lower support areas to remain serviceable during installation without interrupting the clean architectural appearance of the participant-facing sides. Using a shared construction system across these walls also created consistency in proportion, finish and structural behaviour, helping the separate workshop elements read as one integrated scenic package rather than unrelated standalone displays.

    Constructing the Lovable Abu Dhabi Interactive Feature Wall


    The Lovable Abu Dhabi Wall introduced additional three-dimensional and physical interaction into the standard freestanding wall construction. The principal structure was developed using the same timber-framed support methodology, with a plywood base, MDF cladding and a printed vinyl finish across the main participant-facing surface.


    Small MDF boxes were incorporated on both sides of the wall, extending selected parts of the installation beyond the primary display plane and introducing a more layered scenic composition.

    The centre section incorporated 40-millimetre nails positioned according to the approved design. These formed part of the physical interaction system and required accurate placement in relation to the surrounding graphic content.


    Because the wall combined flat graphic surfaces with projecting MDF components and fixed interaction points, workshop setting-out was particularly important.

    The MDF boxes, nails, printed graphics and wall proportions all needed to align correctly so the finished feature operated as one coordinated assembly rather than a collection of separately added components.


    The internal timber frame and counterweighted plywood base provided the concealed support required for the projecting elements while maintaining the overall stability of the freestanding wall. This combination of structural fabrication, applied graphics and participant-facing details transformed the wall from a conventional display surface into a more dimensional interactive scenic feature.

    Integrating Clear Acrylic into the AD Map Wall


    The AD Map Wall combined conventional scenic wall construction with an integrated transparent display element. The primary structure was fabricated using timber framing, a plywood base and MDF cladding, with printed vinyl graphics applied across the main wall surfaces.

    A precision groove was formed within the front fascia to receive a three-millimetre clear-acrylic panel.


    This construction method allowed the acrylic to become part of the wall assembly rather than appearing as a separately fixed surface attached over the front of the scenic structure.


    A light-green painted border framed the acrylic section and created a visual separation between the transparent map area and the surrounding printed graphics. The integration required careful coordination between the groove dimensions, acrylic panel size, painted perimeter and vinyl layout.


    Maintaining the correct fit was important both visually and technically, as the acrylic needed to sit securely within the scenic fascia while remaining clean and accurately aligned with the surrounding graphic information.


    The completed wall therefore combined solid MDF construction, painted detailing, printed vinyl and clear acrylic within one layered architectural composition.

    This approach added material contrast to the wider retreat environment while retaining the structural language used across the other freestanding workshop walls.

    Building the Projected Longevity Wall


    The Longevity Wall was developed as a layered scenic structure rather than a conventional flat graphic backdrop. The primary installation used timber-framed internal construction with a plywood base and MDF cladding, finished with printed vinyl graphics across the main surfaces.

    Its defining feature was the incorporation of three projecting wall sections extending forward from the principal display plane.


    Each projection was individually finished with vinyl, allowing the graphic treatment to continue across multiple architectural surfaces rather than being contained within a single flat elevation.

    The projecting elements introduced physical depth into the installation and created a stronger sense of hierarchy within the wall composition.


    Their fabrication required accurate dimensional control so the three sections aligned correctly with the main wall while maintaining consistent spacing and clean edge relationships.

    The concealed timber framing provided the necessary support for both the primary wall and the forward scenic sections, while the plywood base and lower counterweight system maintained the stability of the complete freestanding assembly.


    By translating the graphic design into a series of layered physical planes, the Longevity Wall demonstrated how scenic fabrication could extend a two-dimensional workshop concept into a more architectural three-dimensional feature.

    Manufacturing the Tinted-Acrylic Workshop Installations


    Evolution Scenic fabricated separate green- and orange-tinted acrylic workshop installations using a layered combination of opaque and transparent scenic materials. Each structure incorporated a plywood base with MDF-clad scenic boxes forming the lower architectural volume.


    Tinted acrylic walls were installed above the base structures and finished with transparent vinyl graphics. This allowed the colour and translucency of the acrylic to remain visible while still carrying the required branded and workshop information. A plain MDF wall formed the backdrop to each installation and was finished with printed vinyl graphics.


    The relationship between the transparent foreground panels and the solid printed background created a layered visual composition that differed from the fully opaque freestanding workshop walls used elsewhere in the retreat. Accurate alignment was required between the tinted acrylic, applied transparent graphics, MDF-clad boxes and rear backdrop surfaces so the complete structure presented as one controlled scenic assembly. Although the green and orange installations used different acrylic colours, they shared the same principal fabrication methodology and material arrangement.


    This repeatable approach allowed the two stands to remain visually related while still creating distinct colour identities within the wider scenic environment. The use of tinted acrylic also introduced a lighter and more translucent architectural quality, providing material variation within the overall project without moving away from the established design language.

    Coordinating Scenic Finishes, Installation & Delivery


    The completed scenic package combined painted surfaces, printed vinyl graphics and transparent vinyl applications across the different wall and acrylic assemblies. Printed vinyl formed the principal graphic finish across the MDF-clad workshop walls and backdrop surfaces, allowing large-format information and branded content to be integrated directly into the scenic construction.


    Paint was used on selected architectural details, including the light-green border surrounding the clear-acrylic panel on the AD Map Wall. Transparent vinyl was applied to the green and orange tinted acrylic panels so the workshop graphics could be introduced without obscuring the colour and translucent character of the acrylic itself.


    Successful delivery depended on close coordination between the fabrication and installation stages. The plywood bases, concealed counterweight supports, timber-framed wall sections, projecting scenic features and acrylic components all needed to align correctly once positioned within the venue.


    Removable rear access panels provided access to the counterweight areas during final placement and adjustment, while the freestanding construction allowed the walls to be installed without permanent fixing to the existing interior architecture. The clear and tinted acrylic components required controlled handling during delivery and installation to protect their visible surfaces and maintain accurate alignment with the surrounding MDF structures and applied graphics.


    Final positioning also needed to preserve the intended relationship between the workshop installations, existing interior elements and circulation areas. Evolution Scenic completed the full scenic build and installation in accordance with the client’s regulations.


    The finished environment brought together scenic carpentry, counterweighted freestanding construction, MDF fabrication, acrylic integration, applied graphics and participant interaction within one coordinated temporary architectural system.

  • Expo Mosque Temporary Architecture and Scenic Construction

    Evolution Scenic temporary mosque façade with triangular portals at Expo City Dubai.

    Constructing a Temporary Mosque at Expo City Dubai


    For Hai Ramadan 2024, Expo City Dubai required a fully functional temporary mosque within a 35m × 35m enclosure. The original tent structure was supplied by another contractor, creating a fixed shell around which the architectural and technical packages had to be developed. Evolution Scenic was responsible for developing the client-supplied design and transforming the basic enclosure through structural fabrication, scenic construction, interior fit-out and building-services installation. The project therefore required the team to work across both architectural and technical disciplines rather than treating the mosque as a conventional event installation.


    Evolution Scenic completed the combined fabrication and site-installation programme over two months. The finished mosque incorporated a structural-steel mezzanine and staircase, double-wall internal construction, a steel-framed external envelope and a developed architectural entrance. Plywood and fibreglass façade elements, illuminated prayer-hall features, fitted joinery and coordinated floor finishes established the visible architectural character of the completed space. At the same time, electrical systems, lighting, air conditioning, plumbing and ablution facilities ensured that the temporary mosque functioned as an operational building rather than solely as a scenic environment.


    The completed installation transformed the contractor-supplied tent into a cohesive temporary place of worship with a distinct architectural identity. Internally, the fitted walls, ceiling treatments, prayer carpet, illuminated mihrab and custom joinery created a controlled worship environment. Externally, the steel-framed envelope, concrete-board construction, façade portals, lattice panels and entrance structure concealed the visual character of the original tent. The result was a coordinated temporary building that combined scenic fabrication, structural engineering, interior fit-out and building services within one integrated delivery package.

    Evolution Scenic plywood and fibreglass portals forming the Expo Mosque façade.

    Developing the Client Design


    The architectural concept was supplied by the client and developed by Evolution Scenic into a practical construction package suitable for fabrication and installation. This required the design intent to be translated into coordinated technical information that could respond to the actual site and structural conditions. The project also had to work around the dimensions and connection restrictions of a tent manufactured by another supplier. Those limitations became an important part of the technical development rather than something that could be resolved only during installation.


    The existing tent influenced the positioning of the internal wall lines, external framing, mezzanine, staircase, façade geometry, foyer, ceiling and service routes. Each of these elements needed to be coordinated with the original enclosure while still maintaining the intended architectural proportions of the mosque. The new construction also had to conceal the visual character of the tent so that the finished environment did not read as a temporary enclosure with decorative panels applied over it. This required a more complete scenic and architectural treatment around both the interior and exterior surfaces.


    Evolution Scenic therefore developed internal and external wall systems that established independent architectural planes around the original tent structure. These controlled surfaces created a consistent basis for installing the façade, entrance features, interior finishes and other scenic elements. By separating the visible architectural treatment from the original enclosure, the team could maintain cleaner geometry and a more convincing finished appearance. The result was a coordinated temporary environment in which the underlying tent structure was visually transformed through scenic construction and architectural detailing.

    Evolution Scenic developed the technical design from the concept renders.

    Fabricating the Structural-Steel Mezzanine


    A mezzanine level was introduced within the mosque to increase the available internal space and make more effective use of the existing tent volume. Evolution Scenic fabricated both the mezzanine structure and the associated staircase from structural steel. The assembly had to fit within the restricted height and footprint of the existing enclosure while maintaining usable circulation around the main prayer area. This required the mezzanine geometry to be coordinated carefully with the wider architectural layout rather than treated as an independent platform.


    The mezzanine formed part of an occupied temporary building and therefore required a robust structural approach appropriate to its function. It was not developed as a lightweight scenic deck or purely visual feature, but as a usable upper level within the completed environment. The staircase also formed part of this circulation strategy, providing access between levels while fitting within the spatial limitations of the tent. Together, the steelwork and access route needed to support the practical use of the space without disrupting the organisation of the prayer areas below.

    The mezzanine fabrication also needed to coordinate with the internal wall construction, air-conditioning distribution, lighting and completed floor levels. These interfaces were important because the structural steel could not be developed in isolation from the surrounding architectural and technical systems. Accurate coordination helped ensure that the finished mezzanine integrated cleanly into the wider temporary mosque environment. 

    Evolution Scenic structural-steel mezzanine and staircase inside the temporary mosque.

    Reinforcing the Internal Tent Walls


    Evolution Scenic constructed a double-wall system around the interior of the tent to replace the soft visual character of the original enclosure with a more controlled architectural finish. The confirmed wall build-up used 18mm plywood PSB board fixed over timber formers, creating a rigid surface suitable for the internal scenic treatment. A textured painted finish was then applied to complete the wall system and establish a consistent visual language throughout the mosque interior. This construction created cleaner wall planes and gave the temporary structure a more permanent architectural appearance.


    The internal wall system also provided a consistent background for the prayer hall, illuminated mihrab, shoe-storage joinery, ceiling treatments and other integrated scenic features. By introducing independent wall planes inside the tent, Evolution Scenic could coordinate these elements against a stable fabricated surface rather than the flexible tent lining. This helped maintain alignment between the architectural features and the wider interior composition. The wall construction therefore performed both a visual and practical role within the completed temporary mosque.


    The internal build also needed to accommodate electrical, air-conditioning and other service interfaces without disrupting the finished wall surfaces. Openings, penetrations and service routes had to be coordinated within the timber former and board construction so that the technical systems could remain integrated with the architectural treatment. This allowed the completed walls to retain clean, continuous planes while supporting the operational requirements of the occupied space. The result was a coordinated internal envelope that combined scenic fabrication, architectural finishing and technical integration within the existing tent structure.

    Evolution Scenic double-wall interior built with plywood PSB board and timber formers.

    Building the External Wall System


    Steel-framed concrete-board panels formed the mosque’s external wall system and created a more substantial architectural envelope around the existing tent. The steel framing provided a stable backing structure that was independent of the original fabric surface. Concrete board was then used as the visible external substrate, giving the perimeter a more rigid and durable finish. The project page confirms this steel-framed concrete-board construction as the principal external wall build-up.


    This external system also created the base for the mosque’s repeated architectural portals, perforated screens and tower-like entrance feature. By working from a controlled structural surface, these elements could be aligned more consistently across the elevations. The wall system therefore supported both the practical enclosure of the tent and the architectural detailing applied to its exterior. This helped the completed mosque read as a coordinated temporary building rather than an exposed tent with added decorative features.


    The external walls played both a functional and scenic role within the overall project. They enclosed and visually transformed the original structure while providing the surfaces required for the repeated façade language. The combination of steel framing, concrete-board panels and applied architectural elements established a continuous perimeter treatment around the mosque. The result was a stronger temporary envelope that supported the scale, rhythm and visual identity of the finished building.

    Steel-framed concrete-board walls enclosing the contractor-supplied temporary mosque structure.

    Creating the Plywood and Fibreglass Façade


    The external elevations were defined by a repeated sequence of tall triangular portals that established the main architectural rhythm of the mosque façade. Evolution Scenic fabricated these features using plywood and fibreglass, combining shaped scenic construction with a more refined visible finish. The portals projected outward from the main wall line, giving the elevations additional depth and helping the temporary structure read as a purpose-built architectural environment. Their repeated geometry became one of the strongest visual characteristics of the completed exterior.


    Each portal needed to maintain consistent angles, openings and spacing so that the elevation remained visually controlled from one end of the building to the other. Any dimensional variation between the individual units could have disrupted the alignment of the façade and created inconsistencies where the portals met the adjacent lattice panels. Plywood provided the shaped scenic base required to establish the angular geometry, while fibreglass was used to form and finish the visible architectural surfaces. This combination allowed the repeated forms to retain a consistent profile across the full exterior treatment.


    Perforated decorative lattice panels were integrated within the façade composition and positioned inside the large angular openings created by the portals. These panels introduced an additional layer of pattern and depth without competing with the dominant triangular geometry of the exterior. The construction photographs show the latticework working in direct relationship with the portal framing, creating a layered façade rather than a flat wall treatment. Together, the plywood, fibreglass and perforated panels produced a coordinated scenic envelope with a strong architectural identity.

    Evolution Scenic plywood and fibreglass portals forming the Expo Mosque façade.

    Fabricating the Prayer-Hall Ceiling


    Evolution Scenic delivered the prayer-hall ceiling together with its circular illuminated feature, creating one of the main architectural focal points within the worship space. The central element comprised a series of illuminated concentric forms that introduced depth and visual emphasis overhead. Its circular geometry contrasted with the surrounding linear surfaces while remaining integrated into the overall interior composition. The completed feature is clearly visible in the project imagery as a defining element of the prayer hall.


    The ceiling treatment needed to coordinate closely with the electrical installation, lighting system and air-conditioning outlets serving the space. This required the illuminated feature to be developed alongside the technical services rather than treated as an isolated decorative component. Lighting positions and service interfaces had to work within the surrounding ceiling geometry while preserving the intended appearance of the concentric forms. The result was a coordinated overhead treatment in which scenic fabrication and technical integration operated together.


    Rather than being applied as a separate decorative object, the illumination formed part of the architectural composition of the prayer hall. The surrounding ceiling lines and wall surfaces helped frame the circular feature and strengthen its visual relationship with the rest of the interior. This created a controlled connection between the overhead geometry and the prayer carpet below, reinforcing the organisation of the worship space. The finished ceiling therefore combined scenic construction, integrated lighting and interior coordination within a single cohesive architectural feature.

    Prayer-hall ceiling construction incorporating lighting and air-conditioning service details.

    Creating the Illuminated Mihrab


    An illuminated triangular mihrab formed the principal focal point at the front of the prayer hall and established a clear visual direction within the worship space. Its geometry continued the triangular architectural language used across the external façade, creating a direct connection between the mosque’s interior and exterior treatment. The feature was designed to sit within the wider wall composition rather than read as an isolated decorative element. This helped maintain a consistent architectural language throughout the temporary structure.


    The mihrab was integrated with Evolution Scenic’s lighting and electrical package, allowing illumination to form part of the feature itself. Rather than relying on applied graphics or temporary branding, the lighting defined the triangular outline and gave the element a restrained visual presence. The illuminated edge treatment helped distinguish the mihrab from the surrounding wall surfaces while preserving the overall simplicity of the prayer-hall environment. This approach supported the functional importance of the feature without introducing unnecessary visual complexity.


    The completed mihrab remained visually clear within the wider prayer-hall composition while retaining the restrained material language used throughout the mosque. Its shape, position and illumination worked together to reinforce its role as the principal architectural reference point at the front of the space. The surrounding wall and ceiling treatments supported the feature without competing with it. The result was a cohesive focal element that linked scenic fabrication, integrated lighting and the wider architectural geometry of the mosque.

    Evolution Scenic illuminated triangular mihrab within the completed prayer environment.

    Integrating Air Conditioning


    Evolution Scenic also supplied the air-conditioning system required to serve the temporary mosque environment. The system needed to operate across the full 35m × 35m enclosure, supporting the main prayer hall, mezzanine, foyer and separate ablution spaces. Because these areas had different spatial conditions, the air-conditioning installation needed to be coordinated with the wider architectural layout rather than treated as a standalone technical package. This helped ensure that the completed environment remained comfortable while preserving the intended internal appearance.


    Air-conditioning outlets and service routes were coordinated with the internal wall construction and ceiling treatment so that the technical systems could be incorporated without disrupting the finished scenic surfaces. The distribution needed to work around the prayer-hall ceiling, mezzanine structure, wall build-ups and other architectural features already forming part of the interior. This required close coordination between the mechanical installation and the scenic fabrication package during design development. The result was a more integrated interior in which environmental services could operate without visually dominating the architectural treatment.

    Completed Expo Mosque combining structural fabrication, scenic construction and building services.

    Constructing the Ablution Areas


    Separate ablution facilities were constructed for men and women as part of the wider temporary mosque environment. Evolution Scenic delivered the partitions, plumbing systems, ablution fittings and vinyl flooring required for both areas. The project information confirms the provision of two separate ablution spaces together with the vinyl floor finish. These facilities formed an essential functional component of the mosque and therefore needed to be integrated into the overall architectural and service layout.


    The ablution areas required coordination between water services, fittings, partitions and floor finishes to create practical wet-use environments. Their positioning also needed to maintain clear separation from the main prayer area while remaining connected to the mosque’s circulation routes. Vinyl flooring provided a maintainable surface appropriate to the wet-area function and supported the practical use of the facilities. The completed spaces therefore combined plumbing, partitions, fittings and finishes within a coordinated part of the temporary building.

    Men’s ablution area with Evolution Scenic plumbing, fittings and vinyl flooring.

    Producing the Shoe-Storage Joinery


    Custom shoe-storage joinery and counters were installed within the mosque to support the transition between the entrance areas and the carpeted prayer hall. These elements provided a practical location for footwear storage while helping organise movement into the main worship space. The joinery needed to offer sufficient storage without obstructing circulation routes or creating congestion around the entrance. Its placement therefore formed part of the wider spatial planning of the mosque rather than functioning as standalone furniture.


    The finishes were coordinated with the surrounding interior so that the shoe-storage units and counters appeared as integrated architectural elements. Their proportions and positioning needed to work with the adjacent wall treatment, flooring and circulation paths while maintaining a clean visual appearance. This approach helped the operational furniture remain consistent with the wider material language of the mosque instead of reading as temporary event equipment. The completed joinery therefore combined practical storage, circulation support and coordinated scenic finishing within the overall interior environment.

    Custom shoe-storage joinery installed beside the temporary mosque prayer hall.

    Installing the Floor Finishes


    Different floor finishes were selected across the mosque to suit the practical requirements of each functional area. The main prayer hall received fitted prayer carpet, while vinyl flooring was installed within the foyer and the separate ablution areas. Grass carpet completed the external approach and immediate perimeter, creating a distinct transition between the outside environment and the enclosed worship space. This material division is confirmed by the project page and helped differentiate the worship, circulation, wet and external zones.


    The floor-finishing package also required careful coordination with the wider construction sequence. Structural steelwork, high-level construction, wall finishing and service installation needed to progress without damaging the completed prayer carpet, vinyl flooring or external grass carpet. Final surfaces therefore had to be introduced at the appropriate stage of the build so they could remain clean and protected through completion. The finished flooring contributed both functionally and visually to the overall organisation of the temporary mosque environment.

    Patterned prayer carpet completing the main worship area at Expo City Dubai.

    Coordinating the Two-Month Programme


    Evolution Scenic completed the combined fabrication and installation programme over two months, bringing together a wide range of interdependent scenic, structural and technical disciplines. The programme covered structural steel fabrication, carpentry, plywood construction, fibreglass work, concrete-board installation, paint finishes, joinery, lighting, electrical systems, air conditioning, plumbing and flooring. Because the existing tent formed a fixed structural interface, each package had to be developed around its actual dimensions and connection limitations. This required the sequencing of fabrication and site works to remain closely coordinated so that one trade could progress without restricting the installation of another.


    Workshop accuracy was essential, but the project also required sufficient flexibility on site to accommodate the real geometry of the contractor-supplied enclosure. The programme needed to move logically from structural and supporting works through wall systems, architectural finishes, service installation, joinery and final flooring while maintaining access for multiple disciplines. Careful coordination was particularly important where steelwork, scenic construction and technical services occupied the same areas of the temporary building.

    Evolution Scenic lattice and façade installation within the angular entrance portals.

    Delivering Functional Temporary Architecture


    The completed mosque demonstrates how scenic construction can extend beyond conventional stages, exhibitions and branded event environments into functional temporary architecture. Evolution Scenic applied its fabrication capabilities to create an occupied building environment incorporating structural elements, building services, wet facilities and a fully developed architectural interior. Although the original tent remained the primary enclosure, it no longer defined the appearance or character of the finished mosque. Instead, the visible environment was created through a coordinated combination of scenic construction, architectural detailing and technical integration.


    Internally, reinforced wall systems, fitted prayer carpet, illuminated architectural features, custom joinery and coordinated services established the main worship environment. Externally, steel-framed walls, concrete-board cladding, plywood and fibreglass portals, decorative lattice panels and the tower-style entrance created a completely different architectural identity around the original enclosure. These elements worked together to transform the tent from a temporary shell into a purpose-built visual and functional environment. The finished mosque therefore operated at the intersection of scenic fabrication, temporary architecture and interior fit-out.


    The project also demonstrates the importance of coordinating multiple disciplines within a single delivery package. Structural construction, specialist manufacturing, lighting, electrical systems, air conditioning, plumbing, joinery and finishing all had to work within the same constrained temporary structure. Each package contributed to the final architectural result while also supporting the practical requirements of an occupied place of worship. The completed installation therefore reflects Evolution Scenic’s ability to combine technical coordination, custom fabrication and detailed finishing within one integrated temporary building solution.

    Image description
  • Pedjas Kraft Coffee Shop Solid-Walnut Interior Fit-Out in Dubai

    Walnut flooring installed around the bespoke coffee shop counter and fitted joinery.

    Project Overview


    Pedjas Kraft Coffee Shop was created within an empty commercial unit in Business Bay, Dubai, in 2023. The project involved transforming the vacant shell into a permanent and fully operational coffee shop environment. Working from a client-supplied concept, Evolution Scenic developed the interior design into a coordinated and buildable solution. The approach combined the functional requirements of a hospitality space with a cohesive architectural and material identity.


    Delivered over a five-week programme, the principal fabrication scope centred on the main service counter and worktops, forming the operational and visual focus of the interior. Bespoke wall shelving, full-height storage, a menu-board frame and glazed display cabinets were produced to integrate service, storage and product presentation within the overall design. Entrance elements were also fabricated to create a considered transition into the coffee shop. Each component was developed as part of a coordinated interior rather than as an individual standalone element.


    The wider fit-out incorporated timber ceiling beams, custom table tops and walnut flooring, creating a warm and consistent material character throughout the space. Engraved branding was integrated into the fabricated elements, embedding the Pedjas Kraft identity directly within the interior. Associated electrical works were coordinated alongside the fabrication and installation process. Together, these elements transformed the original commercial shell into a cohesive, functional and carefully detailed coffee shop.

    Evolution Scenic solid walnut service counter and shelving at Pedjas Kraft Coffee Shop.

    Design Development


    Evolution Scenic developed the client’s initial concept into a coordinated and buildable interior package, translating the design intent into a series of bespoke fabricated elements. The approach considered how the counter, storage, display features and architectural finishes would work together within the existing commercial unit. This allowed the different components to form a consistent interior rather than appearing as separate installations.


    The main service counter established the operational centre of the coffee shop, combining a customer-facing feature with the practical requirements of daily service. Behind it, open display shelving and full-height cupboards provided integrated areas for product presentation and storage. A purpose-made menu-board frame was incorporated into the rear joinery, visually connecting the menu display with the surrounding cabinetry. Timber ceiling beams and supports for suspended lighting extended the material language above the counter and helped define the main service area.


    Custom entrance elements continued the design language at the shopfront, creating a considered transition into the interior. Bespoke table tops carried the same attention to material and detailing into the customer seating areas, while integrated branding reinforced the identity of Pedjas Kraft throughout the space. Together, these fabricated elements created a cohesive relationship between the operational, architectural and customer-facing areas of the coffee shop.

    Custom menu display frame coordinated with walnut shelving and service joinery.

    Fabrication and Materials


    Solid walnut formed the principal material language throughout the fitted interior, giving the coffee shop a consistent timber character across both architectural and functional elements. Evolution Scenic used the material throughout the bespoke fabrication package, including the main service counter, worktops, shelving, storage joinery and menu-board frame. The same approach extended to the entrance elements, ceiling supports and custom table tops, creating continuity across the customer-facing and operational areas.


    The walnut components received a teak-oil finish, enhancing the depth and warmth of the timber while allowing its natural grain, tone and variation to remain visible. Rather than concealing the characteristics of the material, the finish emphasised the crafted quality of the fabricated elements. Engraved Pedjas Kraft logos were incorporated into selected table tops, embedding the branding directly into the manufactured timber surfaces rather than relying entirely on applied graphics.


    Evolution Scenic also installed the confirmed walnut flooring, extending the timber palette across the horizontal surfaces of the interior and reinforcing the overall material identity. This created a visual relationship between the flooring, furniture and bespoke joinery throughout the coffee shop. Other visible floor finishes formed part of separate supply packages and were not included within Evolution Scenic’s confirmed scope.

    Bespoke walnut table tops fabricated by Evolution Scenic for the coffee shop interior.

    Project Outcome


    The completed Pedjas Kraft Coffee Shop is defined by a consistent solid-walnut material language extending across the service counter, worktops, shelving, storage joinery, custom table tops, overhead features and flooring. Together, these elements establish a strong visual connection between the operational and customer-facing areas of the interior. The coordinated use of timber also gives the completed space a warm, crafted character appropriate to a permanent hospitality environment.


    A teak-oil finish was applied across the fabricated walnut components, helping unify the different elements while retaining the natural grain, tone and variation of the timber. This consistency of material and finish allowed individually manufactured components to read as part of a single interior scheme. Integrated details, including engraved branding, further connected the Pedjas Kraft identity with the physical fabrication of the space.


    The project demonstrates Evolution Scenic’s ability to combine interior design development with specialist carpentry, bespoke manufacturing, electrical coordination and on-site installation. From developing the client’s initial concept through to fabrication and final installation, the work brought multiple disciplines together within a five-week programme. The result was the transformation of an empty commercial unit into a cohesive, functional and permanently installed coffee shop interior.

    Evolution Scenic completed walnut joinery across the empty-shell coffee shop interior.
  • LIV Golf Riyadh Scenic Entrance And Interactive Installations

    Daytime view of the scenic entrance portal and circular rotating golf-ball feature.

    Building The LIV Golf Riyadh Scenic Environment


    LIV Golf Riyadh took place at Riyadh Golf Club from 6 to 8 February 2025. The project required a series of temporary scenic structures designed to establish a consistent physical identity across the entrance, wayfinding areas and interactive installations, while supporting the scale and energy of the wider event environment.


    Evolution Scenic developed the detailed scenic package from a client-supplied concept, translating the creative direction into a coordinated fabrication and installation scope. The confirmed works included the main entrance cladding, dimensional logos, integrated lightboxes, striped floor treatment, a two-metre rotating golf-ball sculpture and its circular platform, a six-metre Range sign, an illuminated IBC maze and the complete nineteenth-hole putting installation.


    Rather than relying on a single scenic feature, the environment used several different forms of construction and fabrication. The main entrance operated as a large-scale piece of temporary architecture, combining structural framing, cladding, illuminated branding and graphic finishes. The golf ball functioned as a large-format automated scenic prop, while the Range tower introduced height and illuminated wayfinding within the wider site.


    The IBC maze used repeated modular containers to create an immersive walkthrough environment, with integrated lighting transforming the units into illuminated scenic walls. Within the maze, the putting installation added an interactive component that combined scenic fabrication, artificial-grass surfaces, dimensional branding and integrated lighting.


    Each element required a different combination of materials, fabrication techniques and installation methods, but all were coordinated through the same graphic, lighting and finishing language. This allowed the separate structures to read as one connected scenic environment across Riyadh Golf Club.

    Transforming A Scaffold Into A Scenic Entrance


    The entrance began with a supplied scaffolding structure, which provided the primary temporary support but needed to be fully concealed within the finished scenic design. Evolution Scenic installed a secondary framework using aluminium rectangular tube, creating the required planes for the scenic facade while establishing secure fixing positions for the ACP panels, dimensional logos, lightboxes and other visible details. This approach allowed the underlying scaffold geometry to be transformed into a clean and controlled architectural entrance.


    The entrance needed to read as a deliberate architectural elevation rather than as cladding applied to a temporary frame. Careful panel setting-out ensured the ACP surfaces aligned around the two entrance openings and provided a consistent background for the illuminated line details and large-scale branding. Dimensional LIV Golf lettering occupied the upper section of the facade, with the Riyadh identification positioned below, while additional logos and illuminated graphic elements were integrated across the front elevation and around the entrance openings.


    The scenic treatment continued beyond the vertical entrance structure and onto the approach surface. A striped floor treatment was matched to the client’s specified Pantone colours, extending the visual identity across the complete arrival experience. By combining the scaffold support, aluminium secondary framing, ACP cladding, dimensional branding and integrated lighting, Evolution Scenic created a coordinated temporary architectural installation in which the structural and decorative elements worked together as a single finished environment.

    Fabricating And Engineering The Rotating Golf-Ball Sculpture


    A two-metre branded golf ball formed the principal sculptural feature in front of the entrance. The sphere was fabricated from CNC-machined foam, allowing the overall shape and repeated dimple pattern to be produced with consistent geometry across the large surface. Following machining, the foam form received a fibreglass coating, creating the finished outer shell and preparing it for the final scenic finish and applied LIV Golf branding.


    The golf ball was designed as a moving scenic feature rather than a static prop. Evolution Scenic designed and fabricated the rotation mechanism, developing the sculpture, central shaft, mounting arrangement and supporting structure as connected components. The system needed to support the completed sphere while maintaining a controlled rotational axis, with the visible mounting elements kept visually secondary to the sculptural form.


    The completed golf ball was mounted vertically within a custom circular platform positioned in front of the entrance. Artificial grass, painted finishes and dimensional branding helped integrate the base into the wider golf-themed environment while defining the moving feature within the arrival area. The finished installation brought together CNC fabrication, fibreglass finishing, scenic engineering and controlled movement to create a prominent kinetic focal point for the entrance.

    Turning IBC Units Into Scenic Architecture


    The IBC maze used 1,000-litre intermediate bulk container units as its main construction module.

    Rather than concealing the industrial containers, the installation used their visible grid frames and translucent tanks as part of the scenic appearance.


    The units were arranged into long walls, internal routes and stacked tower forms. Their repeated size gave the installation a consistent construction rhythm and allowed larger masses to be created from a standard component.


    This approach transformed individual storage containers into a temporary architectural system.

    The maze was not dependent on applied graphics alone. Its primary visual effect came from the relationship between the modular units, their stacking arrangement and the light transmitted through their translucent surfaces.


    Evolution Scenic supplied the custom LED system used across the maze. Resolume control enabled colour changes and programmed effects to operate across the complete installation.

    Lighting therefore changed the visual reading of the same physical structure without requiring the container arrangement itself to move.


    During daylight, the maze remained visibly constructed from IBC units. At night, the illuminated tanks formed connected fields of colour, turning the industrial components into scenic lightboxes.

    Integrating The Nineteenth-Hole Putting Feature


    The interactive putting installation was positioned within the IBC environment as a dedicated playable feature within the wider scenic experience. Its main scenic form consisted of a circular illuminated portal reached by an artificial-grass ramp. Raised side structures defined the playing route and helped guide participants towards the target, while layered coloured finishes and integrated lighting gave the piece a strong visual identity that connected with the surrounding illuminated maze.


    A dimensional nineteenth-hole sign occupied the top of the portal, with a smaller golf-ball detail incorporated into the centre of the sign. The combination of dimensional branding, lighting and shaped scenic construction helped establish the feature as a focal point while maintaining a clear connection to the golf theme.


    The artificial-grass playing surface continued directly through the circular opening, creating a strong relationship between the scenic form and the putting activity itself. This meant the structure could not be developed purely as a decorative backdrop. Its geometry had to preserve a practical and visually clear route towards the target while keeping the portal, side walls, lighting details and dimensional signage balanced as one complete composition.


    Together, the fabricated portal, illuminated side details, artificial-grass surface and dimensional signage formed a single integrated interactive installation, combining scenic fabrication with participant engagement inside the wider LIV Golf Riyadh environment.

    Fabricating The Six-Metre Range Feature


    The Range sign provided a separate vertical marker within the wider site, helping define the area through a combination of height, dimensional branding and integrated illumination.


    Its primary support was a six-metre-high scaffold tower. Evolution Scenic added the scenic branding and fully DMX-controlled lightbox, creating a high-level illuminated feature that could remain visually prominent and legible after dark. The sign used dimensional lettering rather than relying only on a printed banner, giving the installation greater depth and allowing the illuminated letterforms to stand out more clearly within the night-time environment.


    As with the main entrance, the structural support and scenic finish needed to operate as a coordinated assembly. Fixing positions, access for lighting installation, cable routing and final sign alignment all depended on the geometry of the scaffold tower. The six-metre height also introduced additional installation considerations, making wind loading, secure fixing and scaffold certification important parts of the overall delivery.


    The completed feature combined temporary scaffold engineering with dimensional scenic fabrication and controlled lighting, creating a strong vertical landmark that complemented the wider LIV Golf Riyadh visual environment.

    Six-metre Range sign scaffold tower with a fully DMX-controlled scenic lightbox.

    Coordinating Materials And Custom Scenic Fabrication


    The project used a broad material palette selected to suit the structural, visual and interactive requirements of each element. Steel and aluminium provided framing and secondary support, while MDF, plywood and painted timber were used for shaped scenic components, platforms and custom-built features. ACP formed the clean external surfaces of the main entrance, while acrylic and polycarbonate supported illuminated details and light-diffusing elements.


    CNC-machined foam and fibreglass were used for the two-metre rotating golf-ball sculpture, while vinyl graphics, printed panels and artificial grass helped carry the LIV Golf visual identity across the site. Evolution Scenic also fabricated a freestanding illuminated logo using a steel-framed structure with an acrylic lightbox, along with custom plywood truss-base covers finished with paint and printed fabric banners.


    The VIP seating area was designed and fabricated with a custom raised platform, carpet finish, coordinated seating and a perimeter handrail. Within the IBC maze, the 1,000-litre units provided both modular structure and illuminated scenic surfaces, with their steel cages and translucent tanks becoming part of the final visual treatment.

    Delivering A Complete Outdoor Scenic Environment


    The confirmed programme covered approximately one month of fabrication and installation. The outdoor setting required the project to account for weather exposure, wind loading and certified scaffold systems while coordinating multiple scenic structures across Riyadh Golf Club.


    At the entrance, the supplied scaffold provided the primary support before Evolution Scenic installed the aluminium secondary frame, ACP cladding, dimensional branding, lightboxes and illuminated details. The rotating golf-ball feature required the positioning of its circular platform, mechanical system and two-metre sculpture, while the six-metre Range structure combined scaffold support, dimensional branding and DMX-controlled illumination.


    The IBC maze was assembled from repeated 1,000-litre units before the custom LED system was installed and connected through Resolume control. The nineteenth-hole putting feature, freestanding illuminated logo, VIP seating platform and custom truss-base covers were also installed as part of the wider scenic environment.


    Wind loading, weather protection and scaffold certification were confirmed considerations, particularly for the entrance facade, Range tower, freestanding lightbox, stacked IBC units and rotating golf-ball sculpture. Following the tournament, the complete temporary scenic installation was dismantled.


    The finished environment brought together temporary architecture, sculptural fabrication, mechanical movement, illuminated branding and interactive construction. From the ACP-clad entrance and rotating golf ball to the IBC maze, putting feature, VIP seating area and supporting branded elements, the project demonstrated how multiple scenic disciplines could be coordinated into one unified LIV Golf Riyadh experience.

  • Qudwa–PISA Forum Scenic Fabrication at Expo 2020 Dubai

    Evolution Scenic modular Qudwa–PISA stage and LED surrounds at Expo 2020 Dubai.

    Building a Modular Forum Environment at Expo 2020 Dubai


    The Qudwa–PISA Global Competence Forum took place at Expo 2020 Dubai on 19 February 2022. Developed around the theme Preparing Students to Live in an Interconnected World, the forum was delivered in collaboration with the OECD and the Bussola Institute.


    Evolution Scenic was responsible for developing and delivering the physical scenic environment. The scope extended well beyond the main presentation area and included the stage deck, screen structures, Media Hub installation, partitions, branded backdrops, illuminated totems and plinths, signage, wayfinding and lounge elements.


    Each part of the environment performed a different function, but the complete installation needed to operate as one coordinated piece of temporary architecture. This required the stage, technical displays, exhibition structures, branding and supporting elements to share a consistent architectural and graphic language throughout the forum.

    Developing the Scenic Concept


    Evolution Scenic developed the scenic design rather than working solely from a completed third-party production package. This allowed the visual concept, fabrication methodology, material choices and installation requirements to be considered together from the beginning of the project.


    The forum identity was translated into a combination of solid scenic surfaces, framed technical displays, illuminated vertical elements and areas of coloured transparency. The main stage established the strongest architectural expression, with the same visual principles subsequently carried into the Media Hub, partitions, branded structures and wayfinding elements.


    Maintaining this continuity was particularly important because the forum contained several distinct functional areas. Consistent proportions, framing, materials and graphics allowed each zone to retain its own purpose while still reading as part of the same temporary environment.

    Constructing the Main Stage


    The main stage and stage deck formed the central scenic structure within the forum. Evolution Scenic fabricated the physical stage environment, including the deck, surrounding scenic architecture and the metalwork required to integrate the LED screens supplied by Evolution Technical.


    MDF, plywood and timber framing formed part of the confirmed material palette. These materials provided adaptable scenic surfaces that could be produced in modular sections and finished with the required graphics and decorative treatments, while metal framing provided additional structural support around the technical display systems.


    The screens were treated as integral parts of the stage composition rather than freestanding pieces of equipment. Their positions influenced the proportions of the surrounding architecture, while the fabricated scenic elements established the visual boundaries that connected the displays to the wider stage.


    The stage also needed to support practical technical operation. Scenic surrounds were therefore developed around the physical requirements of the screens and their supporting systems, allowing the visible architecture and technical installation to work together as one coordinated environment.

    Integrating the LED Systems


    Evolution Technical supplied the LED screen systems used within the main stage. Evolution Scenic fabricated the metal structures and scenic surrounds that incorporated those displays into the architecture of the presentation environment.


    This required accurate coordination between the dimensions of the technical equipment and the fabricated scenic components. Screen position influenced the spacing, alignment and overall geometry of the surrounding structures, while the scenic architecture determined how the technical equipment was visually framed from the audience position.


    The resulting stage combined two connected disciplines. Evolution Scenic created the physical architecture, while Evolution Technical delivered the display systems operating within it, allowing structural, scenic and technical elements to appear as parts of one resolved composition.


    The same collaborative approach extended beyond the main auditorium into the Media Hub, where fabricated frames, graphics and technical displays again needed to operate within a shared architectural system.

    Fabricating the Media Hub


    The Media Hub was developed as a freestanding scenic feature within the wider forum environment. Evolution Scenic fabricated metal-framed panels incorporating coloured transparent sheet and printed graphics, creating a distinct secondary zone without requiring permanent modification to the Expo venue.


    The metal frames established the geometry and structural definition of the feature, while the transparent coloured materials introduced layering and visual depth. Unlike solid scenic walls, these surfaces allowed parts of the surrounding environment and structural framing to remain visible, creating a lighter architectural treatment.


    Printed graphics were incorporated within the framed composition to connect the Media Hub visually with the wider Qudwa–PISA identity. The relationship between structural frames, transparent panels and graphic surfaces allowed the installation to remain distinctive without feeling disconnected from the main stage environment.


    Evolution Technical supplied the display equipment incorporated into the Media Hub. The scenic framing was therefore developed around the technical components so that screens, coloured materials and printed graphics aligned as one coordinated installation.

    Producing Partitions and Branded Backdrops


    Custom partitions and branded backdrops were fabricated to define different areas throughout the forum. These elements functioned as temporary spatial architecture, providing visual separation, branded surfaces and controlled backgrounds without becoming permanent interventions within the Expo venue.


    The confirmed construction palette included MDF, plywood, timber framing, metal framing, acrylic, printed fabric and vinyl graphics. Timber-framed panel construction allowed the larger elements to be manufactured as modular sections, while MDF and plywood provided smooth surfaces suitable for consistent graphic and decorative finishes.


    Metal framing was incorporated where freestanding structures required additional support or where the construction needed to relate visually to the screen surrounds and Media Hub. This created continuity between the heavier scenic walling and the lighter framed structures positioned elsewhere within the environment.


    Together, the partitions and backdrops extended the architectural language beyond the main stage. They helped organise the venue spatially while providing a consistent physical framework for branding, interpretation and circulation.

    Branded Totems, Plinths, Signage and Reception Counters


    Evolution Scenic fabricated MDF totems and plinths finished with vinyl graphics to create smaller branded focal points throughout the forum. These elements extended the visual identity into areas where a full scenic wall or large architectural installation was unnecessary.


    Reception counters, signage and wayfinding used the same coordinated approach to graphics, proportions and finishes. Their scale was smaller than the principal scenic structures, but their positioning and appearance were important to maintaining continuity through the visitor journey.


    The freestanding nature of these elements allowed them to be placed according to the practical needs of each area while remaining visually connected to the wider environment. Their finishes and graphic treatment ensured that supporting functions such as reception, information and navigation became part of the overall scenic language.


    By carrying the design into these smaller components, the temporary architecture extended beyond the main visual moments. The complete forum environment could therefore maintain a consistent identity from the principal stage through to the supporting circulation and reception areas.

    Creating Lounge and Seating Areas


    Evolution Scenic fabricated MDF totems and plinths finished with vinyl graphics to create smaller branded focal points throughout the forum. These elements extended the visual identity into areas where a full scenic wall or large architectural installation was unnecessary.


    Reception counters, signage and wayfinding used the same coordinated approach to graphics, proportions and finishes. Their scale was smaller than the principal scenic structures, but their positioning and appearance were important to maintaining continuity through the visitor journey.


    The freestanding nature of these elements allowed them to be placed according to the practical needs of each area while remaining visually connected to the wider environment. Their finishes and graphic treatment ensured that supporting functions such as reception, information and navigation became part of the overall scenic language.


    By carrying the design into these smaller components, the temporary architecture extended beyond the main visual moments. The complete forum environment could therefore maintain a consistent identity from the principal stage through to the supporting circulation and reception areas.


    Coordinating Externally Supplied Banners


    Tall floor-supported graphic banners were produced by an external specialist supplier and incorporated into the wider forum layout. Evolution Scenic coordinated these elements alongside its fabricated stage, partitions, framed displays and branded structures.


    Maintaining a clear distinction between packages was important. The banners formed part of the final visual environment but were not manufactured by Evolution Scenic, while the surrounding scenic architecture and fabricated elements remained within Evolution Scenic’s direct production scope.


    The positioning of the banners still needed to respond to the scale and layout of the scenic installation. Their graphic presence contributed to the wider visual identity and therefore needed to sit comfortably alongside the dimensional structures, screens and branded surfaces developed elsewhere in the venue.


    Large temporary environments frequently involve several specialist contractors working together. The Qudwa–PISA environment demonstrates how externally supplied elements can be incorporated into a coordinated scenic scheme while retaining clear responsibility for individual fabrication packages.

    Modular Workshop Fabrication


    The complete scenic environment was produced in modular sections, allowing the main stage structures, framed panels, partitions and backdrops to be manufactured away from the venue under controlled workshop conditions.


    Modular construction made the larger elements more manageable for transportation and load-in. Instead of moving complete full-scale structures, the fabrication team could prepare controlled sections that were transported separately and assembled in their final positions at Expo 2020 Dubai.


    This approach placed particular importance on workshop accuracy. Connections needed to align consistently, framed structures had to remain square and graphic surfaces needed to meet cleanly once individual modules were joined together on site.


    The stage surrounds also had to correspond accurately with the dimensions and positions of the technical displays. Completing this coordination during fabrication reduced the amount of adjustment required within the venue and supported a more controlled installation process.

    Completing the Two-Day Installation


    The complete on-site scenic installation was delivered over two days. Modular construction and detailed workshop preparation allowed a substantial proportion of the physical production to be completed before the scenic package arrived at Expo 2020 Dubai.


    The stage deck and modular scenic sections were assembled before the fabricated surrounds were coordinated with the LED screens supplied by Evolution Technical. The relationship between the screens and scenic architecture could then be checked as the primary presentation environment came together.


    The Media Hub was installed as a separate scenic feature, combining its metal frames, coloured transparent panels, printed graphics and technical displays. Partitions, branded backdrops, illuminated totems, plinths, reception elements, signage, wayfinding and lounge structures were positioned across the wider forum environment.


    Externally supplied graphic banners were also incorporated into the final layout. Delivering multiple zones within the two-day installation required a controlled sequence so that structural assembly, technical installation, graphics and final scenic finishing could progress efficiently alongside one another.

    Creating a Unified Temporary Environment


    The completed Qudwa–PISA Global Competence Forum brought scenic fabrication, technical integration and temporary architecture together within one coordinated environment. The main stage combined a modular deck, fabricated scenic structures, metal screen surrounds and LED displays to create the principal presentation setting.


    The Media Hub introduced a different architectural character through freestanding metal frames, coloured transparent materials, printed graphics and integrated technical displays. Partitions and backdrops established the surrounding spatial structure, while illuminated totems, plinths, signage and wayfinding extended the visual identity throughout the venue.


    Lounge and reception elements brought the same design approach into the functional areas supporting the main programme. Externally supplied banners were coordinated within the overall layout, allowing specialist packages to contribute to the completed environment without blurring responsibility for their manufacture.


    Following the forum, the installation was dismantled. From initial scenic development through workshop fabrication, technical coordination, two-day installation and final removal, the project demonstrates the operational value of connecting scenic and technical disciplines within one temporary architectural system. Evolution Scenic produced the physical environment while Evolution Technical supplied the integrated LED and Media Hub systems, with both disciplines coordinated as parts of the same finished space.

  • UAE Climate Tech Conference and Exhibition Scenic Fabrication

    Evolution Scenic illuminated main stage and curved LED backdrops for UAE Climate Tech in Abu Dhabi.

    Engineering the UAE Climate Tech Environment at Abu Dhabi Energy Center


    The inaugural UAE Climate Tech forum was held on 10–11 May 2023 at Abu Dhabi Energy Center. It was organised by the Ministry of Industry and Advanced Technology in partnership with ADNOC and Masdar.


    Evolution Scenic was responsible for the complete scenic scope across the conference and exhibition environment. The project extended from the principal conference stage into the lobby, sponsor areas, exhibitor stands, interaction zones, registration points, breakout spaces and outdoor exhibition areas. More than 80 exhibitor stands formed part of the wider delivery, alongside sponsor booths, custom furniture and display units.


    Because each space had a different function, the scenic system needed to accommodate several wall heights, flooring treatments, display configurations and graphic finishes while retaining a consistent project identity.


    Evolution Technical supplied the LED screens and their supporting systems. Evolution Scenic delivered the scenic surrounds, fabricated structures, graphics, counters and specialist floor details required to integrate those technical components into the wider environment.

    Building a Unified Conference and Exhibition System


    The scenic package was developed as a sequence of connected environments. The main conference room established the primary architectural language through a large central display, curved side screens, illuminated floor lines and a stepped stage.


    This language continued through the exhibition spaces using painted walling, printed graphics, LED skirting and integrated digital screens. Sponsor and exhibitor stands introduced reflective vinyl flooring with further LED strip details. These illuminated lines connected the stand floors visually with the stage steps and scenic outlines in the main room.


    Outdoor stands used a related but simplified material combination of painted scenic walling, printed vinyl graphics, LED displays and exhibition carpet. Registration and breakout spaces were provided with custom reception counters using painted finishes. These counters supported the operational requirements of the venue while remaining visually connected to the wider scenic package.


    The result was a temporary architectural system capable of changing scale and function without losing its material or visual continuity.

    Constructing the Main Stage and Stepped Deck


    The main stage measured 21.5 metres long, seven metres deep and 750 millimetres high. Its surface was finished in exhibition carpet, providing a consistent presentation area across the full stage footprint.


    Stepped access was incorporated at the front and sides of the platform. LED strips followed the step profiles, making the changes in level visually clear and introducing illuminated lines into the stage architecture.


    The LED detailing was also extended across selected floor lines. These routes helped define the stage perimeter and connected the main platform with the curved scenic structures positioned at each side. An illuminated lightbox logo was built into the front fascia. Rather than applying branding as a flat graphic, the lightbox created a three-dimensional feature with its own internal illumination.


    The stage deck, step geometry, carpet, lighting channels and fascia needed to be developed as one assembly. LED positions had to be established before the visible floor finish was completed so that the lighting appeared integrated rather than surface-mounted.


    Integrating the Main Screen and Curved Side Displays


    The principal LED display was an existing screen measuring 18 metres wide and 7.5 metres high.


    This fixed screen established the scale and centre line of the conference stage. The new scenic construction was coordinated around its position and dimensions. Curved LED displays were positioned on both sides of the central screen. Each screen measured four metres by 2.5 metres and was integrated into a scenic wall measuring four metres by 3.5 metres.


    The scenic walls incorporated projecting returns. These returns enclosed the edges of the screen structures and helped connect the technical displays to the surrounding stage architecture.


    Painted finishes and illuminated line details continued across the screen surrounds. This prevented the side displays from appearing as freestanding technical units disconnected from the main stage. Evolution Technical delivered the LED screens and supporting systems. Evolution Scenic coordinated the adjoining walls, returns, floor details and visible finishes.


    This division of scope required accurate dimensional exchange between the scenic and technical teams. Screen supports, wall edges, floor lighting and stage geometry all needed to correspond before the final surfaces were completed.

    Fabricating the Lobby Exhibition Environment


    The lobby exhibition environment was developed around scenic walls reaching three metres in height, creating a consistent architectural framework across the exhibition area. The walls were finished in paint and printed vinyl graphics, allowing individual exhibitor identities to be introduced while maintaining a coordinated overall appearance. LED strips positioned along the skirting created a continuous illuminated base detail and helped visually connect the different wall sections throughout the lobby.


    Digital displays were integrated directly into the scenic walls according to the individual stand designs. Their positions needed to be coordinated with the surrounding graphics, wall geometry, structural supports and visible panel joints so that the screens appeared as part of the scenic construction rather than as separate technical additions.


    Curved wall sections were incorporated alongside the straighter exhibition elements, introducing changes in direction and helping shape movement through the lobby. This allowed the exhibition environment to avoid a repetitive linear booth layout while creating more varied sightlines between adjacent stands.


    The combination of painted scenic surfaces, printed vinyl graphics, integrated digital displays and illuminated skirting gave each exhibitor a defined communication zone while preserving the shared architectural language of the wider UAE Climate Tech environment.


    The completed lobby therefore functioned as both an exhibition setting and a coordinated scenic circulation space, with the wall geometry, digital content and lighting details working together as one temporary architectural system.

    Delivering Sponsor and Exhibitor Stands


    Sponsor stand walls reached 3.5 metres in height, giving the principal partners stronger visibility within the exhibition environment and creating a clear distinction from the surrounding lobby areas.


    The stands used painted wall finishes, printed vinyl graphics and integrated LED screens according to the approved designs. LED strips were positioned at skirting level, continuing the illuminated detail established throughout the wider exhibition space. Reflective vinyl flooring introduced a distinctive finish within the sponsor and exhibitor areas. The surface reflected the surrounding screen content and lighting, adding visual depth while maintaining a clean and consistent scenic finish.


    Additional LED strips were incorporated into the flooring. These illuminated lines were coordinated with wall positions, screen locations and circulation edges so that the lighting detail remained continuous across each stand. The combination of painted scenic walling, printed graphics, integrated displays and illuminated flooring allowed each sponsor and exhibitor environment to retain its own identity while remaining part of the overall UAE Climate Tech scenic language.


    The repeated stand delivery also required consistent fabrication across multiple individual environments. Graphic positions, screen openings, skirting details and floor junctions were carefully controlled to maintain a uniform standard throughout the exhibition.

    Developing the Interaction, Registration and Breakout Areas


    The Gasha interaction area incorporated scenic walls at heights of 2.5 metres and three metres, creating a varied architectural profile within the space. Using two wall heights helped establish separation and visual hierarchy without relying on one continuous wall level throughout the environment. The interaction-area walling remained connected to the wider exhibition system through coordinated scenic finishes and integrated display positions.


    Registration and breakout areas were fitted with custom reception counters finished in paint, providing dedicated points for arrival, information and operational support.


    The counters were developed to sit naturally within the surrounding scenic environment. Their proportions and finishes were coordinated with the exhibition walling so that the functional furniture appeared as part of the overall fabrication package rather than as separately sourced equipment.


    Together, the interaction walls and reception counters extended the same construction and finishing language used across the lobby and sponsor areas while responding to the different operational requirements of each space.

    Extending the Scenic Package Outdoors


    Outdoor exhibition stands formed part of Evolution Scenic’s complete project scope, extending the scenic language beyond the internal exhibition areas.


    These structures used painted scenic finishes, printed vinyl graphics and integrated LED screens in accordance with the individual stand designs. The same attention to wall geometry, branding and display integration used indoors was carried through to the exterior environments.


    Exhibition carpet was used for the outdoor flooring rather than the reflective vinyl specified within the interior sponsor and exhibitor areas. This created a practical distinction between the two settings while maintaining continuity with the carpeted main stage.


    The outdoor stands required coordinated installation of scenic walling, digital displays, graphics and floor finishes so that each element aligned correctly within the completed structure. By carrying the same fabrication and finishing principles outdoors, Evolution Scenic maintained a consistent project identity across both the internal and external exhibition environments.

    Coordinating Installation, Technical Delivery and Compliance


    The complete fabrication and installation programme was carried out within the dates and working periods requested by the client. Evolution Scenic followed the client’s rules, regulations and site instructions throughout the project.


    The installation required close coordination between the main stage, existing venue screen, new curved displays, exhibition walls, sponsor stands, registration counters, specialist flooring and graphic applications.


    Evolution Technical installed the LED screens and their supporting systems, while Evolution Scenic delivered the surrounding scenic structures, wall finishes and flooring details. This required the scenic and technical teams to work within a coordinated installation sequence.


    Screen supports and technical elements needed to be positioned before adjoining scenic finishes and floor interfaces were completed, helping maintain accurate alignment between the displays and surrounding fabrication.


    All client-required project documentation and technical requirements were addressed, and the complete scenic package was delivered within the approved programme without delay or extension.

    Completing the Project Without Programme Extension


    Evolution Scenic completed the full scenic scope within the required client timeline. The finished conference room combined a 21.5-metre stage, exhibition-carpet finish, illuminated stepped decking, lightbox fascia branding, an 18-metre main display and two curved side-screen structures.


    The exhibition areas extended the same design language through three-metre lobby walls, 3.5-metre sponsor structures, varied-height interaction walls and more than 80 exhibitor stands.


    Painted scenic surfaces, printed vinyl graphics, LED skirting, embedded screens, reflective vinyl flooring and illuminated floor lines were coordinated across the individual environments. Outdoor stands, registration counters, custom display units and breakout features completed the wider scenic package.


    The final result demonstrated Evolution Scenic’s capacity to manage conference scenery, exhibition fabrication, digital-screen integration, specialist flooring, graphics and multi-zone installation within one controlled delivery programme. The project was delivered without delay or programme extension.